COMMERCE BUSINESS DAILY ISSUE OF JULY 8,1998 PSA#2132Alliant Techsystems Incorporated, Allegany Ballistics Laboratory, P.O.
Box 210, State Route 956, Rocket Center, WV 26726 N -- RELOCATE MIXERS SOL PHC-235 POC Patrick H. Cunningham,
304-726-5047 The scope of work consists of the removal of a
five-gallon, a one-gallon and (3) one-pint mixers and all associates
hardware from their existing mixing facilities and relocating and
re-installing the same mixers into new mixing facilities that are
already complete. Each mixer relocation and re-installation includes
updating the mixers with new controls and instrumentation, wire and
cable, piping and fire protection. Estimated total cost of the effort
is between $800,000 and $1,100,000. Bid date is not firm, but will be
approximately August 24, 1998. Bonds will be required. West Virginia
Contractors License must be submitted prior to commencement of work by
Contractor and all Subcontractors. In order to obtain plans and
specifications, please submit a $35 non-refundable fee payable to
Alliant Techsystems with a written request. Alliant reserves the right
to refuse requests for plans and specifications on/after July 22,
1998. Posted 07/06/98. (0187) Loren Data Corp. http://www.ld.com (SYN# 0056 19980708\N-0001.SOL)
N - Installation of Equipment Index Page
|
|