COMMERCE BUSINESS DAILY ISSUE OF JULY 16,1998 PSA#2138DA, Tulsa District, Corps of Engineers, P.O. Box 61, Tulsa, OK
74121-0061 C -- ADAL SQUADRON OPERATIONS FACILITY AT TINKER AIR FORCE BASE
OKLAHOMA SOL DACA56-98-R-0019 DUE 081998 POC Jack Schaefer, A-E
Contracts Section, (918)669-7041 or Lisa Samilton, Military Design
Section, (918)669-7154 1. CONTRACT INFORMATION: A firm fixed-price
architect-engineer contract will be negotiated for the concept,
preliminary, and final design for the subject project. All work must be
performed by or under the direct supervision of licensed professional
engineers and/or architects. Required services consist of all work
related to the preparation of plans, specifications, construction cost
estimates, studies, and permit applications. Construction support
services including shop drawing reviews, field consultation, design
modifications, operation and maintenance manuals, and as-built drawing
preparation may be awarded as an option. This procurement is
unrestricted. The anticipated contract award date is August 1998. All
responders are advised that this requirement may be canceled or revised
at any time during the solicitation, evaluation, selection, and
negotiation, and that final award date may vary and final completion
date may vary. If a large business is selected for this contract, it
must comply with FAR 52.219-9 regarding requirements for a
subcontracting plan on that part of the work which it intends to
subcontract. For your information, the subcontracting goals for Tulsa
District are 65% for small business, 10% for small disadvantaged
business, and 5% for woman-owned business. 2. PROJECT INFORMATION: This
project consists of a 1,842 SM addition to the AWACS Mission Squadron
Operations Facility. The facility will have provisions for
administration, training scheduling, briefing, personal equipment
maintenance, and storage for air crews. There will be restrooms and
locker rooms. Space must be included for the commander and his staff.
Supporting systems include utilities, lighting, and site improvements.
Estimated construction cost is between $1M and $5M. Metric scale is
required on construction drawings. Selected A-E will be required to
produce CADD drawings compatible with MicroStation software (5.0 or
higher) of Bentley Systems, to access a computerized Automated Review
Management Systems (ARMS) via modem, and to produce cost estimates
using M-CACES Gold. 3. SELECTION CRITERIA: See Note 24 for general
selection process. The selection criteria in descending order of
importance are: A. Past performance on DoD and other contracts with
respect to cost control, quality of work, delivery schedule,
compliance, history of working relationships with consultants, timely
construction support, and overall cooperation and response. B.
Experience: 1) Recent specialized experience and technical competence
of the firm and/or consultants in the planning and design of squadron
operations facilities. 2) Design within cost limitations. 3) Design
quality management procedures-coordination between disciplines and
subcontractors. (comparable experience of the firm and consultants on
projects completed within the last five years will be given the
greatest weight.) C. Geographical location with knowledge of probable
site locality, conditions, materials and supplies availability, and
applicable regulatory requirements. D. Qualified registered
professional personnel with experience in the following disciplines,
but not limited to: project management, architectural, electrical,
mechanical, fire protection, civil, structural, cost estimating,
geotechnical, and surveying. Particular focus will be on the
qualifications of the personnel with relevant experience on similar
projects. E. Sufficient capacity to complete the design by May 1999
with emphasis on the staff to be assigned on the project and ability of
the firm to ensure timely response to requests for on-site support. F.
Volume of DoD contract awards in the last 12 months as described in
Note 24. 4. SUBMITTAL REQUIREMENTS: See Note 24 for general submittal
requirements. Interested firms having the capabilities to perform this
work must submit one copy of SF 255 (and a SF 254 for the prime firm
and all consultants) to the above address no later than 4:30 p.m. on 19
Aug 98. Solicitation packages are not provided. This is not a request
for proposal. The SF 255 should specifically address the requirements
of this announcement. Responding firms are requested to clearly
identify those tasks to be performed in-house and at what office, and
those tasks to be subcontracted and at what office. Responding firms
are requested to reference clients by name and telephone number for
their three most recent similar designs in Block 10 of their SF 255.
Also in Block 10 of the SF 255 describe the firm's project-specific
design quality control plan, including coordination with
subcontractors. Cover letters and extraneous material are not desired
and will not be considered. Personal visits to discuss this contract
will not be scheduled. Posted 07/14/98 (I-SN223079). (0195) Loren Data Corp. http://www.ld.com (SYN# 0031 19980716\C-0007.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|