COMMERCE BUSINESS DAILY ISSUE OF JULY 20,1998 PSA#2140USDA -- Forest Service, Fed. Bldg. -- Rm. 101, 250 S. 4th Ave.,
Pocatello, ID 83201 Y -- SPREAD CREEK ROAD CONSTRUCTION & STREAM CHANNEL STABILIZATION,
BRIDGER-TETON NATIONAL FOREST SOL R4-IDAWY-98-10 DUE 091098 POC Tammy
Smith, 208-236-7584 This project consists of constructing a road over
the Spread Creek slide and improving and stabilizing the stream channel
through the slide area. Road work will consist of haul of material and
compaction of material at the site, some excavation, and road
surfacing with aggregate. Stream channel work will include removal of
some material from the stream channel and installation of riprap for
stream channel protection. The project is located about 32 air miles
northeast of Jackson, Wyoming. Estimated start work date is June 1,
1999, with a completion time of 180 days. Cost estimated is between
$100,000 and $250,000. FAX requests for a bid package to 208-236-7503.
Posted 07/16/98 (I-SN224469). (0197) Loren Data Corp. http://www.ld.com (SYN# 0156 19980720\Y-0034.SOL)