COMMERCE BUSINESS DAILY ISSUE OF JULY 21,1998 PSA#214120 CONS/LGCC, PO Drawer 52610, Shaw AFB, SC 29152-2610 Z -- PAINT INTERIOR: REMOVE WALLCOVERING/COVE BASE, PAINT & INSTALL
COVE BASE SOL F3860198Q0208 DUE 072098 POC SSgT Patty Gill, 803 895
6009 x268 This is a combined synopsis/solicitation for commercial
products/service prepared in accordance with the format in FAR subpart
12.6, as supplemented with additional information included in this
notice. This notice constitutes the solicitation, price quotes are
being requested and***** a written solicitation will not be
issued*****. The solicitation incorporates provisions and clauses
identified in FAR subpart 12, FAC 97-3, as required. Standard
industrial classification is 1721. This project will be procured using
commercial item procedures. This procurement is to furnish all labor,
parts, materials and transportation to remove wallcovering, prepare
walls, trim and paint both, approximately 33109 sq. ft of wall
surfaces, also to remove and install approximately 2781 linear feet new
cove base in building 1118.***** Contractor shall be responsible for
field measuring. No specifications/ drawings available.***** Contractor
shall provide paint for the walls and trim; wall paint shall be color
#1107, oatcake, latex enamel. The paint for the trim shall match the
existing trim in color and shall be an oil base semi-enamel. Both
paints shall meet the government specifications and shall be classic 99
as manufactured by Sherwin Williams or proven equal. The contractor
shall remove all wallcovering in halls and atrium both upstairs and
downstairs. The contractor shall fill holes, sand, and prepare walls
and trim to receive paint. The contractor shall apply at least one coat
of primer and two coats of finish The contractor shall remove and
install approximately 2781 linear feet of new vinyl cove base. The cove
base to be purchased and installed shall be 4" high, vinyl, .080 ga.,
color #583 chocolate, as manufactured by Roppe or equal. The cove base
to be installed in accordance with the manufacturer's instructions.
All surfaces to be free of voids and protrusions, smooth, secure, and
professionally completed. The contractor shall prepare walls as
necessary to receive paint. Contractor shall prepare walls to be smooth
including patching all holes, clean, and acceptable. The walls shall be
prepared in accordance with the paint manufacturer's recommendations.
All paint residues shall be cleaned after painting. Remove and
reinstall switch plates, signs, lettering, and other items to permit
proper painting. The contractor will be allowed to work from 6:30 a.m.
to 4:30 p.m. Monday through Friday without any special security
requirements. The contractor shall remove and dispose of all debris off
base and in accordance with environmental specifications. Contractor is
to ensure all debris is removed from job site after installation is
completed. The Building Facility Manager and the Base Civil Engineer
Quality Assurance Evaluator will make inspection of completed work. The
contractor must notify the Facility Manager and The Evaluator at least
one week prior to start of work and upon completion. Delivery is to
SHAW AFB, SC. Requests or questions maybe faxed to the attention of
SSgt Patty Gill at (803)895- 6018. See Note 1. Posted 07/17/98
(W-SN224795). (0198) Loren Data Corp. http://www.ld.com (SYN# 0208 19980721\Z-0043.SOL)