COMMERCE BUSINESS DAILY ISSUE OF SEPTEMBER 25,1998 PSA#2188USDA -- Wenatchee National Forest, Procurement and Property Management,
215 Melody Lane, Wenatchee, WA 98801 Y -- GOOSE/MAVERICK ORV TIE TRAIL CONSTRUCTION, LAKE WENATCHEE RANGER
DISTRICT, CHELAN COUNTY, WASHINGTON SOL RFI R6-17-99-04 DUE 110898 POC
Rosie McDonald, 509/664-2715 This project will be advertised as a
written quotation and is being solicited under the new Simplified
Acquisition Procurement (SAP) rules. This project consists of the
construction of an ORV tie trail from the Lower Chiwawa ORV Trail
#1548, near the Goose Creek Campground, to Maverick Saddle. Project
includes approximately 5.1 kilometers of new trail construction.
Project consists of an upper and lower trail project. The upper and
lower trail projects are connected via an existing road on which there
is no work associated with this project. Items of work include:
Clearing and Grubbing, Excavation and Embankment, Grade Dips, Climbing
Turns, Grid Pavement Trail Stabilization, and a Trail Retaining Wall.
Approximately one mile of this new trail construction is located on
mid-slopes between 65% and 75%, while the remaining portions of new
trail construction are located on more moderate side slopes. Some
blasting will most likely be required to complete the trail
construction. New trail construction shall have 800 mm of tread, and on
the side slopes above 35%, the trail shall be full bench. The
Government Estimate is between $25,000.00 and $100,000.00. No bid or
performance bonds will be required. Alternate Payment Protection
(payment bond) is required. Start work is estimated to be 06/01/99 with
150 calendar days for contract completion. This project is open to
large business. Packages available around 10/06/98. Posted 09/23/98
(W-SN253341). (0266) Loren Data Corp. http://www.ld.com (SYN# 0113 19980925\Y-0004.SOL)
Y - Construction of Structures and Facilities Index Page
|
|