COMMERCE BUSINESS DAILY ISSUE OF OCTOBER 13,1998 PSA#2199Fleet & Industrial Supply Center, Regional Contracts Dept, Attn: Bid
Officer/Code 210A94, 937 N. Harbor Drive, Suite 212, San Diego, CA
92132-0212 J -- BATTERBOARD & DECK PLANKING REPLACEMENT SOL N00244-99-R-0009 DUE
102098 POC Jo Escalera, Contracting Officer, (619) 532-2558 WEB: Click
here for the FAR on-line site., http://farsite.hill.af.mil/VFFARA.HTM.
E-MAIL: Click here for the Contracting Officer,
jo_c_escalera@sd.fisc.navy.mil. 17. This is a COMBINED
SYNOPSIS/SOLICITATION for commercial work prepared in accordance with
the format in FAR Subpart 12.6, as supplemented with additional
information included in this notice. This announcement constitutes the
ONLY solicitation; proposals are being requested and a separate
written solicitation will not be issued. Solicitation Number
N00244-99-R-0009 applies and is issued as a Request for Proposal. This
solicitation document and incorporated provisions and clauses are
those in effect based upon the current Federal Acquisition Circulars
(FAC) current up to FAC 97-8 as provided on-line at
http://farsite.hill.af.mil/VFFARA.HTM . The August 1998 Defense Federal
Acquisition Regulation Supplement (DFARS) and current Departmental
Letters is provided on-line at http://farsite.hill.af.mil/VFDFAR1.HTM
. This announcement is published as a total Small Business Set-Aside
action per FAR 52.219-6. The standard industrial classification is
2439, with a small business size standard of 500 employees and the FSC
is J020. The contractor will perform a full range of REPAIRS FOR
BATTERBOARD AND DECK PLANKING REPLACEMENT FOR VARIOUS NAVAL VESSELS
LOCATED IN THE SAN DIEGO AREA. Support will be for SUPSHIP SAN DIEGO,
CA. The proposed contract will be firm fixed priced, indefinite
delivery/ requirements. Proposed unit prices will be for the Base Year,
Option Year I, and Option Year II. All costs for the three years must
include pricing as outlined in the following Line Items (LI). The
period of performance for the Base Year is 01 November 1998 through 31
October 1999. Option Years, if exercised, will be Option I (01
November 1999 through 31 October 2000) and Option II (01 November 2000
through 31 October 2001). (A) SUPPLIES/SERVICES AND PRICING SCHEDULE:
Item 0001 Batterboard replacement in accordance with the Statement of
Work (SOW) Quantity: 2500 Unit: LF***Item 0002 Deck Planking
Replacement in accordance with the SOW Quantity:5000 Unit:LF***Item
0003 Services and material to empty, clean gas free and certify as safe
for humans and safe for hot work tanks on various naval vessels in
accordance with (IAW)the SOW and SUPSHIP Reference 271-2. Tanks
serviced will be at low suction. Contractor is responsible for disposal
of contaminated fluids IAW local, state, and federal regulations. Note:
LI 0003AA through 0003AD require certification by a Marine
Chemist.***Item 0003AA Tanks up to 2,000 gallon capacity Quantity: 15
Unit: EA ***Item 0003AB Tanks over 2,000 gallon and up to 10,000 gallon
capacity Quantity: 30 Unit:EA ***Item 0003AC Tanks over 10,000 gallon
and up to 30,000 gallon capacity Quantity: 50 Unit: EA ***Item 0003AD
Tanks over 30,000 gallon and up to 60,000 gallon capacity Quantity:10
Unit: EA***Item 0004 Certify as safe for humans and safe for hot work
tanks and voids on various naval vessels by certified Marine Chemists
in IAW the SOW and SUPSHIP Reference 271-2. Quantity: 35 Unit: EA
***Item 0005 Batterboard Brackets Quantity: 15 Unit: 10 EA. ***Item
0006 Accelerated delivery plus a specified percentage (fill-in %) of
the unit prices for items 0001 through 0005 (Approximately 15% of the
work is anticipated to be accelerated). Quantity:1 Unit:Lot***Item 0007
Additional Work -- It is anticipated that additional work may become
necessary during the performance of work ordered by delivery orders to
this contract. The offeror shall fill in the blank spaces below, and
the Resultant values will be used for the purposes of evaluation and
for pricing of any additional work required during performance of the
contract. The total number of labor hours and total material price
shall be negotiated at the time a modification to the delivery order is
processed. Approximately 200 hours straight time and 48 hours overtime
could be involved in undisclosed work. The contractor agrees to
perform this additional work, when authorized by the ACO.***0007AA
Additional Work -- Straight Time Quantity: 200 Unit: HR *** 0007AB
Additional Work -- Overtime Quantity: 48 Unit: HR. Approximately
$5,000.00 worth of parts could be involved in this undisclosed work.
The contractor agrees that parts will be provided at the lowest list
price less any proposed discounts (fill in a percentage (%) which
represents a discount (if not provided, the discount shall be
considered zero (0) %)). Any charges for material handling must be
proposed or will be considered as zero (%) if not provided. ***0007AC
Approximately $5000.00 worth of parts Quantity: 1 Unit: LT ***0008
Contract Data Requirements List, DD Form 1423, Exhibits A and B hereto.
Quantity: 1 Unit: LT Add all line items 0001 through 0008 for a total
price of LOT I -- BASE YEAR Include pricing for the same Description,
Quantity, and Price with renumbered Line Items 0009 through 0016 for
LOT II OPTION YEAR I. Include pricing for the same Description,
Quantity, and Price with renumbered Line Items 0017 through 0024 for
LOT III OPTION YEAR II. Provide a Grand Total for LOTS I, II, AND III.
(B) STATEMENT OF WORK: (Any references to attachments and CDRLs will
be provided as requested by interested offerors. Contact the
Contracting Officer by email). Paragraphs will be renumbered upon
contract award based on the Standard format for SOWs. GENERAL
REQUIREMENTS: ***The contractor shall furnish all services, labor and
material required to accomplish the work based on the terms and
conditions of the proposed contract. ***Attention of the contractor is
directed to the Occupational Safety and Health Act of 1970 (29 U.S.C.
651-678), and to the Occupational Safety and Health Standards for Ship
Repairing (20 CFR-1915) promulgated under Public Law 85-742, amending
Section 41 of the Longshoremen's and Harbor Workers' Compensation Act
(33 U.S.C. 941) and adopted by the Department of Labor as occupational
safety or health standards under Section 6(a) of the Occupational
Safety and Health Act of 1970 (29 CFR 1910.13). These regulations apply
to all ship repair and related work, as defined in the regulations,
performed under this contract or any job order thereunder shall be
construed as relieving the contractor fromany obligations which it may
have for compliance with the fore said regulations. *** Remove from
ship and dispose of wood resulting from batter board and deck planking
replacement as scrap. REFERENCE: All work to be accomplished hereunder
shall be in accordance with the following specifications and/or
references as applicable. (1) NAVSEA Standard Item 009-23 --
Interference's; remove and install Attachment I. (2) NAVSEA Standard
Item 009-12 -- Welding, Fabrication and Inspection Requirement;
accomplish -- Attachment II. (3) NAVSEA Standard Item 009-09 -- Process
Control, Procedure; provide and accomplish -- Attachment III. (4)
Surface Preparation Specifications, Steel Structures Painting Council.
(5) NAVSEA Standard Item 009-06 -- Protection During Surface
Preparation; accomplish -- Attachment IV. (6) NAVSEA Standard Item
009-32 -- Cleaning and Painting Requirements; accomplish -- Attachment
V. (7) BUSHIPS 805-921806, Rev D. Installation of Planking on Deck
Plating. (8) S9086-VG-STM-000/Chapter 634; NSTM, Deck Coverings. (9)
Deck Shimming Details -- Attachment VI. (10) Batterboard Installation;
accomplish -- Attachment VII. (11) Well Deck Planking Installation;
accomplish -- Attachment VIII. (12) NAVSEA Standard Item 009-01 --
General Criteria; accomplish -- Attachment IX BATTERBOARD REPLACEMENT
-- Check point (Installation): ***Remove, template from existing and
replace damaged Batterboards, with new boards, mounting brackets and
studs as specified in individual delivery order and in accordance with
Attachment VII using new galvanized fasteners and washers. ****Wood
shall be Douglas Fir, dense structural #2 or better in accordance with
the current Grading Rules for West Coast Lumber published by the West
Coast Lumber Inspection Bureau and be fire retardant treated in
accordance with MIL-L-19140 using the treatment having the word
"exterior" appearing in the manufacturers designation shown on
QPL-19140. DECK PLANKING REPLACEMENT -- ***Check point (Installation)
***Remove, template from existing and replace damaged deck planking
with new planking, margin boards, deck studs and fastening components
as specified in individual delivery order and in accordance with the
References and Attachment VIII. ***Check point (Shimming) Shim new deck
planking in accordance with Attachment VI. *** After removal of deck
planking studs, Batterboard brackets and Batterboard studs or other
fastening components, weld and grind smooth all depressions and
protrusions resulting from removals. *** Check Point (Surface
preparation) -- For areas of steel bulkheads, deck or other steel
surfaces exposed by deck planking or Batterboard removals accomplish
the requirements of SSPC-SP-10 of C.2.1. Reference d., for areas under
500 square feet and accomplish the requirements of SSPC-SP-11 of
C.2.1. Reference d for areas under 500 square feet. ***CheckPoint
(Contamination Protection) Accomplish the requirements of Attachment IV
when abrasive blasting. Abrasive blasting to be accomplished in a dust
proof enclosure. ***Check Point (Coating application) Preserve each
surface prepared in Check Point (Surface Preparation) in accordance
with Reference #6, including Table 2, Line 2, Columns B, C, and D.
Template from existing and preserve the entire surfaces of each new
Batterboard in accordance with Reference #6, including Table 12, Line
1 Columns B and G. (C) APPLICABLE CONTRACT CLAUSES The following
clauses are hereby incorporated by reference or full text as
appropriate: FAR 52.212-1, INSTRUCTIONS TO OFFERORS -- COMMERCIAL, FAR
52.212-2, EVALUATION -- COMMERCIAL ITEMS, FAR 52.212-3, OFFEROR
REPRESENTATIONS AND CERTIFICATIONS -- COMMERCIAL ITEMS, FAR 52.212-4,
CONTRACT TERMS AND CONDITIONS-COMMERCIAL ITEMS AND FAR 52.212-5,
CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR
EXECUTIVE ORDERS -- COMMERCIAL ITEMS. Addendum to FAR 52.212-1:
52.215-7, Unnecessarily Elaborate Proposals or Quotations; 52.217-8,
Amendments To Solicitations; (b)(4) CONTRACTORS' PROPOSALS: Contractor
shall submit the following information (1) Pricing Schedule (2)
Representation and Certification and (3) Past Performance -- Provide a
minimum of three recent references. 52.212-1, INSTRUCTIONS TO
OFFERORS-COMMERCIAL ITEMS: (a) SIC data included herein; exception to
para (h), the Government anticipates a single contract award;***** FAR
52-212-2, EVALUATION-COMMERCIAL ITEMS, paragraph (a) is completed as
follows; Factor 1, Technical Capability -ability to provide the items
stated herein of the same or better. Factor 2, Past Performance --
ability to consistently deliver and maintain quality and timely service
during contract performance period (submit three references as well as
any other sources that may have relevant information). Factor 3,
Price. Factors 1 and 2 are equal in importance. Factors 1 and 2 when
combined are significantly more important than Factor 3, Price -- most
advantageous price considering all other factors. Contract award will
be made based on the requirements of this solicitation to the
responsible offeror whose offer conforming to the solicitation will be
the most advantageous to the Government, price and other factors
considered. The Government reserves the right to award without
discussions. ***** Addendum to FAR 52.212-4: 52.216-18, Ordering --
Base Year -- from date of award to one year thereafter and two one year
options; 52.216.21, Requirements; 52.217-8, Option to Extend Services;
52.217-9, Option to Extend the Term of the Contract; 52.219-6 Notice
of Total Small Business Set Aside; 52.232-18, Availability of Funds;
52.237-2, Protection of Government Building, Equipment and Vegetation;
52.247-34 FOB Destination; Designation of Ordering Activity: SUPSHIP
San Diego, CA.***** 52.212-5, CONTRACT TERMS AND CONDITIONS REQUIRED TO
IMPLEMENT STATUES OR EXECUTIVE ORDERS AND INCLUDES THE FOLLOWING
APPLICABLE CLAUSES (a) 52.222-3, Convict Labor and (2) 52.233-3,
Protest After Award ; (b): 52.203-6, Restrictions on Subcontractor
Sales to the Government-Alt 1; 52-203-10, Price or Fee Adjustment for
Illegal or Improper Activity; 52.219-8, Utilization of Small Business
Concerns and Small Disadvantaged Business Concerns; ) ; 52.219-14
Limitation on Subcontracting; 52.222-26, Equal Opportunity; 52.222-35,
Affirmative Action for Special Disabled and Vietnam Era Veterans ;
52.222-36, Affirmative Action for Handicapped Workers; 52.222-37,
Employment Reports on Special Disabled Veterans and Veterans of the
Vietnam Era 252.212-7001,CONTRACT TERMS AND CONDITIONS REQUIRED TO
IMPLEMENT STATUTES OR EXECUTIVE ORDERS APPLICABLE TO DEFENSE
ACQUISITIONS OF COMMERCIAL ITEMS (a) The Contractor agrees to comply
with the Defense Federal Acquisition Regulation Supplement (DFARS)
clause 252.247-7023, Transportation of Supplies by Sea, which is
included in this contract by reference (b) The Contractor agrees to
comply with the following DFARS clauses: 252.205-7000, Provision of
Information to Cooperative Agreement Holders; 52.219-7009, Small
Business and Small Disadvantaged Business Subcontracting
Plan;252-247-7024, Notification of Transportation of Supplies by
Sea.***** OFFERORS ARE REQUIRED TO COMPLETE AND INCLUDE A COPY OF THE
FOLLOWING PROVISIONS WITH THEIR PROPOSALS: FAR 52.212-3, Offeror
Representation and Certifications-Commercial Items; DFARS 252.212-7000,
Offeror Representations and Certifications-Commercial Items (a copy of
the representation and certifications may be downloaded -- see the
on-line web site at
http://farsite.hill.af.mil/reghtml/dfars/dfars252_000.htm). Your
completed proposal may be mailed or hand-delivered to Fleet and
Industrial Supply Center, Bid Desk, to the IMMEDIATE ATTN of: Code
2701, 937 North Harbor Drive, Building 1, Second floor, Contracts
Department, San Diego, CA 92132. Bid Desk Hrs: Mon-Fri, 8:00 am -- 4:00
PM, excluding federal HOLIDAY hours. PROPOSALS MUST BE RECEIVED NO
LATER THAN 3:00 PM, PST, 20 October 1998. FAXED OR EMAIL PROPOSALS WILL
NOT BE ACCEPTED. IMPORTANT NOTICE: DFARS 252-204-7004 "Required Central
Contractor Registration" applies to all solicitations. Lack
ofregistration in the CCR database will make an offeror INELEIGIBLE FOR
AWARD. Please ensure compliance with this regulation when submitting
your quote. Call 1-888-227-2423 or visit the Internet web site at
http://ccr.edi.disa.mil for more information. Note 1 APPLIES. Posted
10/08/98 (W-SN260803). (0281) Loren Data Corp. http://www.ld.com (SYN# 0055 19981013\J-0011.SOL)
J - Maintenance, Repair and Rebuilding of Equipment Index Page
|
|