COMMERCE BUSINESS DAILY ISSUE OF OCTOBER 13,1998 PSA#2199U.S. Department of Labor, ETA, Division of Acquisition & Assistance,
200 Constitution Ave., NW, Room S-4203, Washington, DC 20210 Z -- ASBESTOS ABATEMENT AND INSULATION AT THE TURNER JOB CORPS CENTER
IN ALBANY, GEORGIA SOL IFB-98-DAA-01-JC DUE 120198 POC J.M. Yielding,
RA. AIA, on (912) 435-0036 or Marion Carter, Contract Specialist,
(202) 219-8706 WEB: IFB-99-DAA-01-JC, http://cbdnet.access.gpo.gov.
E-MAIL: IFB-99-DAA-01-JC, carterm@doleta.gov. The work involves the
abatement of asbestos-containing material (ACM) from mechanical
equipment, including pipes (insulation and/or joint compound), tanks,
flues, pumps, strainers, fittings and valves in the Mechanical Rooms of
ten buildings at the Turner Job Corps Center, Albany, Georgia. The ACM
abatement work in one of the ten buildings extends beyond the
Mechanical Room above classrooms and cooridor ceilings. Existing
damaged and/or deteriorated non-ACM insulation in the same ten
buildings' Mechanical Rooms is to be replaced with new insulation. New
insulation is to be installed on some un-insulated pipes in seven of
the ten Mechanical Rooms. ACM abatement, insulation and reinstallation
in two of the ten buildings' Mechanical Rooms will be bid as
add-alternates. The construction completion date of the project is 154
calendar days from Notice to Proceed. The estimated cost range for
construction is between $100,000 to $250,000. Plans and Specifications
shall be available on or about October 27, 1998, only from the
Architect/Engineering firm of Yielding & Wakeford Architects, AIA, 116
Roosevelt Avenue, Suite 200, Albany, Georgia 31702. Contact, J.M.
Yielding, RA, (912) 435-0036 for additional information concerning this
project. Collect calls will not be accepted. It is emphasized that
requests be in writing. Plans and Specifications will be made available
for pick-up at the A/E's office, or delivery may be arranged at an
additional charge. Any additional shipping and or handling charges must
be pre-paid and COD requests will not be accepted. Requests will be
answered on a first-come, first-serve basis until supply is exhausted.
For requests made after the initial supply is exhausted, a
non-refundable fee not to exceed the actual cost of the IFB documents
(to be determined by the Contracting Officer) will be required in order
to obtain the IFB documents. Pre-Bid Walk-Thru is scheduled for
November 10, 1998, at 11:00 A.M. local time at the Center. Bid Opening
is scheduled for December 01, 1998, at 2:00 P.M. local time at the
A/E's office. NOTE: This is a 100% Small Business Set-Aside
Acquisition. The Standard Industrial Classification (SIC) Code for this
acquisition is 1799. See Numbered Note 1. Posted 10/08/98 (W-SN260388).