COMMERCE BUSINESS DAILY ISSUE OF OCTOBER 14,1998 PSA#2200Department of the Interior, U.S. Geological Survey, 345 Middlefield
Road,Mail Stop 285, Menlo Park, CA 94025-3591 N -- REHABILITATION OF MONITORING WELLS SOL 99WRSS0001 DUE 113098 POC
Rita A. Leach, (650) 329-4162, FAX (650) 329-5480 E-MAIL: Click here
to contact the contracting officer via, rleach@usgs.gov. The U.S.
Geological Survey, Water Resources Division, Honolulu, Hawaii, has a
requirement for drilling services on the Island of Guam. The work to be
accomplished under the specifications is to rehabilitate eight (8) deep
monitor wells in Northern Guam for the purpose of obtaining scientific
data on the location and movement of the fresh water saltwater
transition zone and continuous or periodic measurements of water levels
within the Northern Guam Lens. The depth of the wells range from 400
feet to 785 feet. The wells rehabilitated by this work are to serve
indefinitely as scientific observation wells. The wells to be
rehabilitated were drilled into the several limestone formations of
northern Guam. In most cases the limestone is highly permeable and the
possibility exists of loosing circulation due to solution cavities
and/or fractures if drilling is required to remove blockages or to
clean out the well bore prior to installing the casing. If drilling
fluids are required they should consist of air, water and drilling
foam. In no case will drilling mud be used. Three of the wells have PVC
solid casing and screen installed and great care must be used in
cleaning out these wells so that the existing solid casing and screen
is not damaged. The Contractor shall provide one complete rotary
drilling unit, cranes or hoists, all tools, accessories, water, power,
lighting, bits, well casing, gravel and all other equipment, materials
and experienced personnel necessary to conduct the worked described in
the specifications. The drilling unit shall be in good condition and
of such capacity as to be able to operate and clean the well bore while
under as much as 500 feet of water. The Contractor shall supply all
casing, cement, gravel and water for the work. Because some of the work
will be accomplished adjacent to or near residences and/or schools,
suitable mufflers or other noise abatement may be required to comply
with the local noise ordinance. Control of noise, dust, water and
fluids from the drilling are the responsibility of the Contractor, and
must meet all the requirements of all local ordinances. The
rehabilitation of the eight wells shall commence on or before December
15, 1998 and be completed within a period of 60 days. See Numbered
Note 1. Posted 10/09/98 (W-SN261077). (0282) Loren Data Corp. http://www.ld.com (SYN# 0043 19981014\N-0001.SOL)