COMMERCE BUSINESS DAILY ISSUE OF JANUARY 12,1999 PSA#2260Tahoe National Forest, 631 Coyote Street, Nevada City, Ca 95959-2250 Y -- MEYERS WAREHOUSE CONSTRUCTION SOL RFP-17-99-10 DUE 031099 POC
Alan M. James, Contracting Officer, 530-478-6121, FAX 530-478-6126
Proposals are being requested for the design and construction of a
pre-engineered metal warehouse/shop building. The warehouse will
accommodate a variety of uses and disciplines. There shall be a minimum
of one unisex accessible restroom. The foundation and bay doors shall
be a minimum of 10' high (rollups) to accommodate deliveries that
require either a forklift or backhoe. There shall be an equitable split
of floor space based on a total of 12 shares. The shares will aid in
determining the building dimensions and the offeror/contractor shall
provide layout proposals, however, the offeror will not be required to
construct interior walls. Total contract time is 180 days including
design, submittal review and construction, with an estimated start work
date of 05/15/99. Copies of the Project Design Prospectus will be
available 02/08/99. Bonding is required, 20% Bid, 100% Performance, and
50% Payment. The location for the proposed Meyers Warehouse is 3030
Highway 50, So. Lake Tahoe, CA. To reach the location, take Highway 50
east from Placerville to So. Lake Tahoe. Meyers is located on the
north side of the freeway after passing the Agriculture Inspection
Station. The government will award the contract to the offeror whose
offer represents the best value to the Forest Service. Posted 01/08/99
(W-SN286351). (0008) Loren Data Corp. http://www.ld.com (SYN# 0093 19990112\Y-0007.SOL)
Y - Construction of Structures and Facilities Index Page
|
|