COMMERCE BUSINESS DAILY ISSUE OF JANUARY 22,1999 PSA#2267HEADQUARTERS IOC, ATTN AMSIO-ACI, BLDG 350 5TH FLOOR MIDDLE BAY, ROCK
ISLAND IL 61299-6000 56 -- CEMENT, BULK PORTLAND, GENERAL CONSTRUCTION. SOL
DAAA09-99-R-2024 DUE 021199 POC Contract Specialist Marianne Whitmer
(309) 782-6605 (Site Code DAAA09) E-MAIL: whitmerm@ioc.army.mil,
whitmerm@ioc.army.mil. This is a combined synopsis/solicitation for
commercial items prepared in accordance with the format in Subpart
12.6, as supplemented with additional information included in this
notice. This announcement constitutes the only solicitation; proposals
are being requested and a written solicitation will not be issued.
This synopsis/solicitation is issued as Request for Proposal (RFP)
DAAA09-99-R-2024 for the fol lowing: Item 0001 Cement, bulk portland,
general construction type 1, gray color, without air entraining
feature, IAW ASTM C150-97a, to be unloaded by vendor into silo equipped
with four foot high pipe with four inch quick connect. The contracting
office anticipates awarding a Requirements Type Contract for a minimum
quantity of 0 pounds and a maximum quantity of 26,777,140 pounds for
the performance period of 1 October 1999 through 30 September 2000.
Minimum Delivery Schedule is 3 days after issuance of a deliver order.
FOB Destination, McAlester Army Ammunition Plant, 1 C Tree Road,
McAlester, OK 74501-9002. The solicitation and incorporated provisions
and clauses are those in effect through Federal Acquisition Circular
98-01. This procurement is unrestricted. This procurement is Standard
Industrial Classifica tion (SIC) code 5032, small business size
standard is 100 employees. The provision at FAR 52.212-1 Instructions
to Offerors-Commercial items applies. The provision at FAR 52.212-2
Evaluation-Commercial Items applies. Award will be made to the low
responsive, responsible offeror at a fair and reasonable price. Please
note: Offerors shall include a completed copy of the following
provisions: FAR 52.212-3, and DFAR 252.212-7000 Offeror Representations
and Certifications-Commercial Items, with their offers. FAR clause
52.212-4 Contract Terms and Conditions-Commercial Items applies to this
acquisition. FAR clause 52.212-5, Contract Terms and Conditions
Required to Implement Statutes or Executive Orders-Commercial Items
applies to this acquisition and the following clauses apply: 52.203-6,
52.219-8, 52.222-26, 52.222-35,52.222-36, and 52,222-37. DFAR clause
252.212-7001, Contract Terms and Conditions Required to Implement
Statues or Executive Orders Applicable to Defense Acquisi tions of
Commercial Items applies to this acquisition and the follow ing clauses
apply: 252.225-7001, 252.227-7015, 252.227-7037, and 252.247-7024. The
following full text clauses shall apply: 252.211-16-Variation in
Quantity (Apr 1984) (a) A variation in the quantity of any item called
for by this contract will not be accepted unless the variation has
been caused by conditions of loading, ship ping, or packing, or
allowances in manufacturing processes, and then only to the extent, if
any specified in paragraph (b) below. (b) The permissible variation
shall be limited to: 10% percent increase, 10% percent decrease. This
increase or decrease shall apply to all items. (End of Clause)
52.216-18 Ordering. (Oct 1995) (a) Any supplies and services to be
furnished under this contract shall be ordered by issuance of delivery
orders or task orders by the individuals or acti vities designated in
the Schedule. Such orders may be issued from 1 Oct 1999 through 30 Sep
2000. (b) All delivery orders or task orders are subject to the terms
and conditions of this contract. In the event of conflict between a
delivery order or task order and this contract, the contract shall
control. (c) If mailed, a delivery order or task order is considered
"issued" when the Government deposits the order in the mail. Orders may
be issued orally, by facsimile, or by electronic commerce methods only
if authorized in the Schedule. (End of clause) 52.216-19 Order
Limitations (Oct 1995) (a) Minimum order. When the Government requires
supplies or services covered by this contract in an amount of less
than 30,000 pounds the Government is not obligated to purchase, nor is
the Contractor obligated to furnish, those supplies or services under
the contract. (b) Maximum order. The Contractor is not obligated to
honor -- (1) Any order for a single item in excess of 1,000,000 pounds;
(2) Any order for a combination of items in excess of 1,000,000 pounds;
or (3) A series of orders from the same ordering office within three
days that together call for quantities exceeding the limitation in
subparagraph (b)(1) or (2) of this section. (c) If this is a
requirements contract (i.e., includes the Requirements clause at
subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the
Government is not required to order a part of any one requirement from
the Contractor if that requirement exceeds the maximum-order
limitations in paragraph (b) of this sec tion. (d) Notwithstanding
paragraphs (b) and (c) of this section, the Contractor shall honor any
order exceeding the maximum order limita tions in paragraph (b),
unless that order (or orders) is returned to the ordering office within
three days after issuance, with written notice stating the Contractor's
intent not to ship the item (or items) called for and the reasons. Upon
receiving this notice, the Govern ment may acquire the supplies or
services from another source. 52.216-21 Requirements.(Oct 1995) (a)
This is a requirements contract for the supplies or services specified,
and effective for the period stated, in the Schedule. The quantities of
supplies or services spe cified in the Schedule are estimates only and
are not purchased by this contract. Except as this contract may
otherwise provide, if the Government's requirements do not result in
orders in the quantities described as "estimated'' or "maximum" in the
Schedule, that fact shall not constitute the basis for an equitable
price adjustment. (b) Delivery or performance shall be made only as
authorized by orders issued in accordance with the Ordering clause.
Subject to any limita tions in the Order Limitations clause or
elsewhere in this contract, the Contractor shall furnish to the
Government all supplies or ser vices specified in the Schedule and
called for by orders issued in accordance with the Ordering clause. The
Government may issue orders requiring delivery to multipledestinations
or performance at multiple locations. (c) Except as this contract
otherwise provides, the Gov ernment shall order from the Contractor all
the supplies or services specified in the Schedule that are required to
be purchased by the Government activity or activities specified in the
Schedule. (d) The Government is not required to purchase from the
Contractor require ments in excess of any limit on total orders under
this contract. (e) If the Government urgently requires delivery of any
quantity of an item before the earliest date that delivery may be
specified under this contract, and if the Contractor will not accept an
order provid ing for the accelerated delivery, the Government may
acquire the urgently required goods or services from another source.
(f) Any order issued during the effective period of this contract and
not completed within that period shall be completed by the Contractor
within the time specified in the order. The contract shall govern the
Contractor's and Government's rights and obligations with respect to
that order to the same extent as if the order were completed during the
contract's effective period; provided, that the Contractor shall not be
required to make any deliveries under this contract after 31 October
2000. (End of clause) This is a DO rated contract regarding the Defense
Priorities and Allocations System. Faxed proposals IAW FAR 52.215-5 are
acceptable. Fax proposals to (309) 782-4955, Attn: Marianne Whitmer.
Proposals may be mailed to: HDQ, IOC, Attn: AMSIO-ACI-S/ Marianne
Whitmer, Rock Island, IL 61299-6000. Issue date is the date this notice
is published in the CBD. Closing Date: 2:00 P.M. CT, 11 Feb 99. The
provisions at FAR 52.232-18, Availability of Funds applies. The
following full text DFAR clause applies: 252.204-7004, Required Central
Contractor Registration (Mar 1998) (a) Definitions. As used in this
clause- (1) "Central Contractor Regis tration (CCR) database" means the
primary DOD repository for contrac tor information required for the
conduct of business with DOD. (2) "Data Universal Number System (DUNS)
number" means the 9-digit number assigned by Dun and Bradstreet
Information Services to identify unique business entities. (3) "Data
Universal Numbering System +4 (DUNS+4) number" means the DUNS number
assigned by Dun and Bradstreet plus a 4-digit suffix that may be
assigned by a parent (controlling) business concern. This 4-digit
suffix may be assigned at the discretion of the parent business concern
for such purposes as identifying subunits or affiliates of the parent
business concern. (4) "Registered in the CCR database" means that all
mandatory information, including the DUNS number or the DUNS+4 number,
if applicable, and the corresponding Commercial and Government Entity
(CAGE) Code, is in the CCR database; the DUNS number and the CAGE code
have been validated; and all edits have been successfully completed.
(b)(1) By submission of the offer, the offeror acknowledges the
requirement that a prospective awardee must be registered in the CCR
database prior to award during perfor mance, and through final payment
of any contract resulting from this solicitation, except for awards to
foreign vendors for work to be performed outside the United States. (2)
The offeror shall provide its DUNS or, if applicable, its DUNS+4 number
with its offer, which will be used by the Contracting Officer to verify
that the offeror is registered in the CCR database. (3) Lack of
registration in the CCR database will make an offeror ineligible for
award. (4) DOD has established a goal of registering an applicant in
the CCR database within 48 hours after receipt of a complete and
accurate application via the Internet. However, registration of an
applicant submitting and application through a method other than the
Internet may take up to 30 days. Therefore, offerors that are not
registered should con sider applying for registration immediately upon
receipt of this soli citation. (c) The contractor is responsible for
the accuracy and completeness of the data within the CCR, and for
anyliability result ing from the Government's reliance on inaccurate or
incomplete data. To remain registered in the CCR database after the
initial registra tion, the contractor is required to confirm on an
annual basis that its information in the CCR database is accurate and
complete. (d) Offerors and contractors may obtain information on
registration and annual confirmation requirements by calling
1-888-227-2423,, or via the Internet at http://ccr.edi.disa.mil. (End
of clause) Posted 01/20/99 (A-SN289790). (0020) Loren Data Corp. http://www.ld.com (SYN# 0216 19990122\56-0001.SOL)
56 - Construction and Building Materials Index Page
|
|