COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 17,1999 PSA#2284San Manuel Band of Mission Indians, Tribal Administration, P.O. Box
266, Patton, CA 92369 C -- PROFESSIONAL CIVIL ENGINEERING DESIGN FOR TRIBAL GOVERNMENT 23.5
ACRE INDUSTRIAL ANNEX SOL NCO 99-1 DUE 050199 POC William A. Jenson,
Director of Economic Development (909) 382-2222, extension 243 WEB:
none, none. E-MAIL: Wil Jenson, Director of Economic Development, San,
wjensen@sanmanuel.com. I. Introduction The San Manuel Band of Mission
Indians, a Federally recognized Indian Tribe, wishes to obtain
services from a professional engineering firm to prepare design plans,
specifications, and engineering cost estimate for development of an
approximate 23.5 acre industrial park at South NCO Housing Parcel at
former Norton Air Force Base, California. The plans and specifications
must conform to the requirements of the most recent Uniform Building
Code (UBC) and of the City of San Bernardino, and the requirements
listed in standard specifications for Public Works Construction (Green
Book). II. Descriptions of Project The project will consist of two (2)
elements, these include: Element One: (1) The development of a "Colored
Rendering" of South NCO Parcel (approximate 23.5 acres) showing the
placement of "Maximum Buildout" of concrete tilt-up building(s) on the
proposed industrial lot(s). Additional title block on the colored plan
view rendering shall indicate the total square footage of proposed
building construction taking into account a roadway "loop system"
around the parcel as private road. The project shall accommodate
finished grading plans for two (2) pads -- each would provide for
approximately 200,000 square foot (+/-) and one (1) additional pad of
40,000 square foot pad concrete tilt-up building, for phased
development of each building. Element Two: (2) Preparation of parcel
map, engineering plans, specifications, landscape architecture design
plan sheets, and cost estimates for construction including everything
necessary to obtain a permit(s). The "San Manuel Tribal Government
Industrial Annex" is described as a new industrial development to be
constructed consistent with the development guidelines identified in
the land use planning documents identical to San Bernardino
International Trade Center and Specific Plan and City Development
Code(s). This project will be constructed adjacent to the San
Bernardino International Airport property to the south and bordered by
5th street on the north, and 3rd street on the south, with Victoria
Avenue on the east. Approximately 103 housing units currently exist on
the property and underground utility lines transect the property, and
as such, will require engineering demolition plans and coordination in
relocation of the backbone infrastructure. Any approvals from any
utility shall be in written form and be obtained by the engineers from
various agencies to be included as part of the scope of work and made
a part of this RFP. Engineering services and design will include: (1)
Aerial control, Topographic mapping (2) Rough and precise grading plan
sheets Structural calculations for retaining walls, footings, etc, as
appropriate. (3) Erosion control plan & plan sheets. (4) Local storm
drainage plan (this includes all on-site and any off-site storm
drainage plans to drain site into the "Third Street channel"), any
storm drainage structures, hydrology and hydrologic analysis and
calculations. (5) Street improvement plans, including sectionsfor grade
separations detail for access to the property from public roadways. All
roadway profile & sections shall conform to City requirements. Entryway
statement identifying "San Manuel Tribal Government Industrial Annex"
pad and sign design conforming to City Specific Plan requirements.
Concrete parking lot(s), street lighting plans and underground electric
plans, these shall include on proposed improvement plans the location
of all street lighting within 600 feet of the project utility
relocation plan sheet(s) required for relocating power poles, etc.,
with costs identified in writing from each Utility (i.e. cost of
electric, water, sewer, gas etc.) The relocation costs shall include
costs for undergrounding for on-site utility extensions for project,
where appropriate or should this be a requirement for existing
utilities. (6) Legal descriptions and easement documents as required
for any Utility company or by the city. (7) A detailed engineers cost
estimate for each element of construction, detailed in "book form", a
8.5" x 11" file. (8) All construction specifications in "book form"
including documents and easements detailed in separate 8.5 x 11 file.
This shall include detail construction contract documents, plan
details, special provisions, letters of approval of engineering plan
design, and authorization to "Construct over Facilities" from the San
Bernardino City & Water Department, County of San Bernardino Flood
Control District, etc, with subject conditions from these district(s)
made a part of the engineering design and including any permits and
identification of any development agreements or fees. (9) Traffic
control plans, including those required for during construction, as
required for public safety, in addition to the requirements by the City
of San Bernardino (includes coordination with City Engineers and Public
Works Department) (10) Any and all on-site and off-site water plans,
including fire hydrant placement as required by local fire department
or agency and City requirements for hydrant placements; On-site "loop
line" water main system includes stub-out locations for building
sprinkler fire systems hookups for each building pad site; include any
water district or city plan check and inspection fees for water system
(obtain fee cost in letter form). (11) Any and all on-site and off-site
sewer plans, including calculation of sewer connection fees,
calculation of water district plan check and inspection fees (obtain
fee cost in letter form). (12) All geologic study and field
investigation(s) required for human occupancy structures and site
grading plan development. (13) Geotechnical investigation(s) and soils
requirements for site development and grading plan, parking lot design
and grading, building pad design and grading; and for all site
development. (14) Landscape architecture design plan(s) sheets,
including any median requirements, if any,in addition to landscape
architectural for the entire site and open space areas.(include
identification of plan check and inspection fees for irrigation systems
and landscape). (15) A site plan, to be developed to create two (2)
pads (each pad shall accommodate 200,000 sq. foot building), and one
(1) 40,000 square foot building, common parking areas and open space
(parkways) as remainder parcel. (16) Demolition plans for all housing
structures, fences, poles, pavement areas, etc., shall be developed in
accordance with all applicable law and shall include "demolition plan
sheet(s)" and written specifications for all elements requiring
demolition. (17) Engineering design and plan sheets should incorporate
special provisions for lighting and signage requirements, including
secured 10 foot high iron fence gate access control point serving
property, from 5th street. A major part of completing this engineering
design prior to acceptance by the Tribe or final payment will be the
coordination of the engineering firm with San Manuel Department of
Building & Safety. When the Tribe receives the plans from the
engineering firm, the plans shall beconsidered as "permit ready",
meaning they shall not require any plan check submittal changes or
modifications. It is therefore necessary for the engineering firm to
have professional engineering and management expertise, as the tribe
will not authorize any change orders for "plan check revisions". It
shall be the responsibility of the engineering firm to submit a design
for professional engineering services and to make any minor plan check
revisions, if required, prior to the award of any final payment based
on a contract. Any conference, meetings with any outside agency or
pre-screen check meetings held shall include a representative from San
Manuel Economic Development Department. Note: The finished plans shall
include two (2) sets of original "wet-signature" signed original mylar
and one copy of xerox mylar. III. Insurance Requirements Insurance
coverage shall be verified with original wet signature "Certificate(s)
of Insurance" and be sent to the Tribe prior to any contract, if any.
The followingincludes the minimum coverage and requirements by the
Tribe: General Liability $2,000,000.00 Personal Liability $1,000,000.00
Auto Liability $1,000,000.00 Professional Liability $1,000,000.00
Workers Compensation $1,000,000.00 Valuable Papers $1,500,000.00 (Tribe
added as a loss payee) 30 day notice to cancellation requirement on all
policies with the San Manuel Band of Mission Indians ("Tribe") and
Victoria Development, named as additionally insured. This shall be
required to be made part of any contract, if any, prior to any work.
Any and all sub-consultants shall be approved by the Tribe with
identical insurance requirements, identical to above-noted
Certificate(s) of Insurance including the San Manuel Band of Mission
Indians and Victoria Development, named as additionally insured. IV.
Special Provisions The Tribe has P.L. 93-638 ATTG contract, pursuant to
Indian Self Determination and Education Assistance Act, with the BIA,
U.S. Department of Interior. In accordance with the Act, and the Act of
April16, 1934 (48 Stat.596, as amended [25 USCS 452 et. Seq.], or any
other Act authorizing Federal Contracts with or grants to Indian
organization or for the benefit of Indiana, shall require that to the
greatest extent feasible 1) preferences and opportunities for training
and employment in connection with the administration of such contracts
or grants shall be given to Indians; and 2) preference in the award of
subcontract and subgrants in connection with the administration of
such contracts or grants be given to Indian organizations and to
Indian-owned economic enterprises as defined in section 3 of the Indian
Financing Act of 1974 (88 Stat. 77) [25 USCS 1452]. V. Proposal
Requirements Six (6) copies of the proposal shall be submitted to the
San Manuel Band of Mission Indians, by U.S. Postal Mail only,
postmarked no later than March 1, 1999 and delivered to the following
address: San Manuel Band of Mission Indians P.O. Box 266 Patton, CA
92369 Attn: Sealed Bid -- San Manuel Tribal Government Industrial Annex
All proposals shall indicate the following in a detailed manner: 1.
Past experience on similar projects. 2. Staff specifically assigned to
the project at the professional level (include copies of state license
& certificates). 3. Support personnel to be used. 4. consultants, if
any, to be used. 5. A total cost breakdown associated with each task
identified in this proposal (engineering services and design [Items 1
thru 17] ) and shall not-to-exceed costs for each element in
engineering design & fees). 6. A total cost (not to exceed) for the
entire engineering project. 7. A time chart (spreadsheet) showing total
field and office engineering time indicating time-frame for completion
of work, showing this time in calendar time, and shall include any
allowances for review periods. 8. A payment schedule for percentage of
work completed for all elements of engineering design. This "request
for proposals" does not commit the Tribe to award a contract or to pay
any costs incurred in the preparation of a proposal in response to
this request, or to procure or contract for any services. The tribe
reserves the right to accept or reject, in part or in its entirety, the
request for proposal if such action is deemed to be in the best
interest of the Tribe. Proposals will be reviewed and supplemental
interviews will be conducted at a later date and prior to any
selection. Posted 02/12/99 (W-SN298333). (0043) Loren Data Corp. http://www.ld.com (SYN# 0020 19990217\C-0003.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|