COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 23,1999 PSA#2288U.S. Army Corps of Engineers, Jacksonville District, P.O. Box 4970,
Jacksonville, Florida 32232-0019 Y -- PONCE DE LEON INLET NORTH JETTY EXTENSION AND REVETMENT, VOLUSIA
COUNTY, FL SOL DACW17-99-B-0015 DUE 042999 POC Wanda I. Cruz
904-232-2083 WEB: Click here to view further information and bidders,
http://www.saj.usace.army.mil. E-MAIL: Click here to contact the
Contract Specialist, wanda.i.cruz@usace.army.mil). This project
consists of two separate features of work to be constructed along the
north shore of Ponce de Leon Inlet as follows: The first feature will
be the Contract Base Bid portion of work and the second feature will be
the Option Bid portion of the work. (1) The first feature of work
consists of constructing an 800-foot landward extension of the north
jetty to the west, referred to as revetment section #1. The revetment
will tie into the existing north jetty at Station 58+00. The revetment
crest elevation will be +12 feet, MLW, which matches the crest
elevation of the north jetty and the existing topography behind this
portion of the revetment. The crest width will be 12 feet and a front
slope of 1 vertical on 2 horizontal will be constructed down to
elevation -5.5 feet, MLW. A 25-foot scour apron will be constructed at
the toe of the revetment. The base of the structure will be at
elevation -15 feet, MLW. Both revetment and scour apron will consist of
a 2-foot-thick layer of bedding stone that will be placed over nonwoven
geotextile filter fabric and a 7.5-foot-thick layer of armor stone that
will be placed over the bedding stone. The bedding stone will be
standard Department of Transportation graded Florida limerock, with a
density of 140 lbs/ft . Armor stone will be 165 lbs/ft with a median
stone size of 8,500 lbs. The crest of the revetment will be chinked
with bedding stone from elevation +4.5 to +12, in order to decrease the
permeability of the revetment and minimize loss of backbeach material
through the structure. Total quantities of materials required for
construction of revetment section #1 are approximately 35,692 tons of
armor stone, 8,538 tons of bedding stone, 768 tons of chinking stone
(same gradation as bedding stone), 9,780 square yards of filter fabric,
and 60,000 cubic yards of excavation. Material removed during
excavation is to be replaced over toe of revetment and as backfill, to
approximate pre-construction grade. The estimated contract performance
period for revetment section #1 is 9 months, which includes 2 months
for Mobilization and Demobilization. (2) The second feature of work
consists of constructing an approximately 1,540-foot revetment
extending westward from the end of revetment section #1, referred to as
revetment section #2. The revetment crest elevation will be +10 feet,
MLW. The crest width will be 7.5 feet and a front slope of 1 vertical
on 2 horizontal will be constructed down to elevation -15 feet, MLW. No
scour apron will be provided. The revetment will consist of a 1.5-foot
thick layer of bedding stone that will be placed over nonwoven
geotextile filter fabric and a 5-foot thick layer of armor stone that
will be placed over the bedding stone. The same bedding stone
gradations will be used and the crest will be chinked in the same
manner as revetment section #1. The armor stone will be 165 lbs/ft with
a median stone size of 2,500 lbs. Total quantities of materials
required for construction of revetment section #2 are approximately
30,056 tons of armor stone, 8,476tons of bedding stone, 610 tons of
chinking stone (same gradation as bedding stone), 13,000 square yards
of filter fabric, and 40,000 cubic yards of excavation. Material
removed during excavation is to be replaced over toe of revetment and
as backfill, to approximate pre-construction grade. The estimated
contract performance period for the revetment #2 is 6 months. Magnitude
of construction is between $5,000,000 and $10,000,000. Pre-Solicitation
Notice was issued 02/19/99. Invitation will be issued on or about
03/11/99 and open on or about 04/29/99. Solicitation will be issued in
electronic format only. Bidders will be provided a CD ROM at no cost.
Please include telephone and facsimile number, tax identification
number on response request. Request for CD ROM may be made to:
wanda.i.cruz@saj.usace.army.mil. You may respond by facsimile to: ATTN:
KENNETH FAULK at (904) 232-2748. If your response is returned by
delivery service, the street address is 400 West Bay Street, Room 867,
Jacksonville, FL 32202. THIS ACQUISITION IS 100% SET-ASIDE FOR SMALL
BUSINESS. NOTE: Contracting information for the Jacksonville District
is now available at our web site: http://www.saj.usace.army.mil/. You
must be registered in the Central Contractor Registration in order to
be eligible to receive an award from this solicitation. Call
1-888-227-2423 for more information. SIC Code 1629. Size Standard is
$17M Posted 02/19/99 (W-SN300074). (0050) Loren Data Corp. http://www.ld.com (SYN# 0136 19990223\Y-0009.SOL)
Y - Construction of Structures and Facilities Index Page
|
|