|
COMMERCE BUSINESS DAILY ISSUE OF MARCH 9,1999 PSA#2298GSA, FTS, 819 Taylor St. (7ZRE), Fort Worth, TX 76102-6105 D -- TIVOLI EMS INSTALLATION AND INTEGRATION, FORT SAM HOUSTON, TEXAS
SOL 7TF-99-0013 DUE 031599 POC Dorothy M. E-MAIL: Dorothy M.,
shan.clark@gsa.gov. The following are responses to questions regarding
the above-numbered solicitation. The date for receipt of proposals is
extended to 4:30 P.M., Central Standard Time, March 15, 1999. Question
1. What is the number of enterprise servers that will eventually
replace the 100 distributed servers operated and maintained by the Fort
Sam Houston ITBC? The Government expects the contractor to propose an
appropriate number consistent with their technical solution. Is it 75?
Not necessarily -- see answer above. What is the approximate breakdown
amongst the specified enterprise servers like Data, Application,
Internet, Intranet, etc? The Government expects the contractor to
propose an engineering solution (breakdown) consistent with industry
standards. i.e., a certain type of server supports a certain number of
users. Question 2. Is the contractor required to migrate all existing
applications and custom scripts from the existing distributed servers
to the new enterprise servers? No. The contractor is expected to
install and make operational the enterprise servers as well as load
server software. Question 3. Is there an architectural design that
illustrates the load balancing amongst the new enterprise servers,
showing both a projected physical and logical location? No. Question 4.
What is the current hardware platform that HP OpenView is running on
(UNIX, NT)? Is NIS being used? HP open view currently operates on a
HP9725 (HPVX Version 10.1). NIS is not used. Question 5. Will the two
locations (Building 2840 and Building 4190) split the EMS
responsibility or will they act as fully redundant centers? EMS
responsibility will be resident in Bldg. 4190. If they split the
management, what is the anticipated distribution of managed nodes-based
on region or sites? No split-see answer above. What is the availability
of the EMS, will a failover capability be required amongst some of the
tools like HP OpenView? No. Question 6. Is it anticipated that the
enterprise servers function as TMRs and if so, will they be
interconnected (one-way or two- way)? Tivoli Managed Region. Fort Sam
has no plans at this time, they have a Web server; however, there is a
possibility that they could function as TMR in the future.. Question
7. Will DNS server(s)-primary and backup, be setup prior to EMS
integration or will that also be included as one of the tasks? DNS
servers are set up and operational now. How many PDC's and BDC's
presently exist and will consolidation of those be required? About 10
BDC's and 7 PDC's exist; Fort Sam personnel are undertaking
consolidation and so will not be required of the contractor for this
task order. Question 8. What types of monitors are used for the desktop
systems? A 17" SVGA is the standard monitor. Question 9. Will Tivoli's
TEC be used for Event Management? The Government expects the
contractor to propose/recommend the products appropriate to their
technical solution. Question 10. Will Tivoli 3.6 be implemented? The
Government expects the contractor to propose the latest version of
Tivoli. Question 11. Will Microsoft's SMS remain in place for certain
areas of systems management, or will Tivoli modules replace SMS in
parts or all together? The Government expects the contractor's solution
to replace SMS in total. Question 12. Is there a standard
hardware/software configuration for each data, application, internet,
intranet, primary domain controller, etc. enterprise server? The
contractor should propose a standard configuration appropriate to their
technical solution. Question 13. Should HP NNM 6.0 be integrated as
part of the EMS solution as opposed to NNM 4.x? Yes. Question 14. What
are the current version of the tools listed in 2.2.6, for example, New
Bridge Vivid Management Station, HP OpenView Netmetrix, Ungermann Bass
Net Director, etc.? Will any of these tools need to be updated to the
most recent version? Except for New Bridge, Cabletron, and Ungermann
Bass, tools will need to be updated. Question 15. Will training of
technicians, system administrators, and network technicians take place
at each phased delivery/milestone? Or, will the training take place at
the completion of the entire project? A placid approach is preferable,
but the Government will consider other training strategies proposed by
a contractor. Question 16. What backup/recovery software will be used
for the EMS suite of tools? The Government expects the contractor to
propose the appropriate software consistent with their solution.
Question 17. What database software will be used on the enterprise
class servers, MS SQL, Oracle? No database software is planned for
enterprise server use. Question 18. Will all the EMS tools need to be
integrated as part of the pilot? Does the 10% reflect approximately 10
servers and 400 desktops? Yes. Ten servers and 400 desktops are
acceptable as a pilot. Question 19. Will firewall technology
(CheckPoint or Trusted Information Systems) be integrated into the
overall EMS solution? Firewall technology is not planned as part of
this effort. Question 20. Are there any planned network upgrades,
technology migrations, WAN links, etc. that may affect the EMS delivery
schedule? An ATM network upgrade is planned, but currently unfunded.
Therefore, EMS schedule will not be impacted. Question 21. Does the
work have to be done at the client site? Can the tools be staged at a
remote facility and then integrated on the client site over a specified
period of time? Due to the limitations of the network connection into
Fort Sam, the contractor should plan to work at the client site.
Question 22. How many users are anticipated to use the EMS
simultaneously? Approximately 10-15 users may use EMS simultaneously.
Question 23. Is there a preferred vendor of choice (i.e., Dell, Hewlett
Packard) for the enterprise class servers? The Government has no
preference. Question 24. Do Tivoli and any other EMS tools need to be
purchased by the contractor? The contractor is required to provide
Tivoli, EMS tools and any other software consistent with their
solution. Question 25. When is the expected date of award? Award willbe
made following the evaluation process, which is dependent upon the
number of proposals submitted, need for clarification, etc. There is no
specific award date targeted. Question 26. Is all Tivoli to be GFE? See
response to Question 24, above. Question 27. In sections 2.2.1, 2.2.2,
and 2.2.4 the RFP uses the word, "procure." If all Tivoli software is
GFE, what is the Government expecting to be procured? See response to
Question 24, above. Question 28. In section 5.1, the invoice is to
include hours worked and travel expenses yet this is to be a firm,
fixed price contract, where milestone payments are made and costs are
not usually disclosed? Is this to be Firm, Fixed Price as stated, or
Time and Materials as indicated by Section 5.1? The Government expects
to award a Firm, Fixed Price contract. Question 29. Is the 36-month
lease cost for the servers to be proposed as a separate number from the
FFP cost of the Tivoli integration work since leasing infers recurring
monthly charges? If not, then how should the lease be shown under FFP,
given that the work is to end by 30 November, 1999? The contractor
should show sufficient detail in their cost proposal to allow
evaluation of their fixed price offer. As such, the Government expects
sto see the server lease cost(s) identified separately. The contractor
may propose a payment schedule for the Government's consideration.
However, the server lease cost is expected to be invoiced and paid in
euqal monthly installments over 36 months. Question 30. Will the
Government provide RDBMS software for Tivoli or is it to be
vendor-provided? What is the preferrred RDBMS? The Government expects
the contractor to offer RDBMS software appropriate to their solution.
The Government has no preference. Question 31. Paragraph e. of the
solicitation specifies level of effort or firm, fixed price and in
Paragraph 17(xiii), a firm, fixed price only option is provided. Please
clarify. See answer to Question 28, above. Question 32. The number of
servers to consolidate from/to is unclear. What number of servers will
be required for the lease? Has the Government determined the number of
servers to consolidate or is it the contractor's responsibility to
recommend the proper number of servers based on the system/network
assessments to be performed? See response to Question 1, above.
Question 33. What information will be provided for all equipment
(servers, etc.); quantities, configurations and applications in order
to determine the level of effort to price FFP? The Government has
identified sufficient detail in the Statement of Work to allow for firm
fixed price. Question 34. The purpose of the pilot environment is
unclear. What parameters are required for the pilot based on the
products to be procured and consolidation to be completed? The
contractor may propose the pilot's parameters which will serve as a
proof of concept. Question 35. Item 1.2 states, "All servers shall be
engineered and installed to consolidate approximately 100 distributed
servers operated and maintained by the Fort Sam Houston ITBC. The
contractor shall propose a 36-month lease for all servers." Item 2.2.2
states, "Management of servers: The contractor shall identify,
procure, test and implement the capability to remotely manage 75
servers." What is the correct number of servers for the lease? See
response to Question 1, above. Question 36. Is the Tivoli EMS software
going to be purchased or is it part of the lease? The contractor may
propose either. Fort Sam Houston qualifies as an acredited educational
institution and contractors should investigate possible manufacturer
discounts in either case. Question 37. Are there any follow-on or
continuous services required beyond the installation period? The
Government does not expect services beyond the installation period,
except for monthly lease costs. Question 38. What is the network
operating system? Current DOD standard is Microsoft NT, and Unix is
required. Question 39. What is the client operating system? Please see
Section 2.2.1 of the Statement of Work. Question 40. What is the
correct number of Tivoli EMS client software required? 4500 scalable to
7000. Question 41. What is the correct number of Tivoli EMS server
software required? The Government estimates 75. Question 42. Item 3.2.1
through 3.2.6 describes different server uses and different
configuration. What is the quantity needed for each item? The quantity
should be proposed by the contractor with their technical solution to
the Statement of Work. Question 43. Page 1, introductory section. The
FAR Circular 97-8 references section 12 and 19, but not Section 17.
Where may we find this section? All FAR references may be found at the
website http://farsite.hill.afb.mil. Question 44. What is your
definition of a complete turnkey solution? The contractor will provide
all services, software, and hardware to meet the objectives and
requirements of the Statement of Work. Question 45. Paragraph 1.1: What
are the completion criteria and acceptance criteria for the "complete
turnkey solution?" The contractor may propose completion and acceptance
criteria consistent with their technical solution. Question 46.
Paragraph 2.1: Cables are not manageable items. Would you agree to
removing this requirement, or to permit an exemption? A contractor may
propose assumptions, conditions, or exceptions in their proposal. The
Government will evaluate the contractor's proposal based upon the
criteria identified in the solicitation. For now, cables are required.
Question 47. If the systems are not Intel-based, what are they? Some
UNIX and OS2. Question 48 Para 2.2.3: What is the level of integration
desired? Para 2.2.3: Are the networking components at current firmware
levels? Are they all SNMP-manageable in their current state? See answer
to Question #14 above. Question 49. Para 2.2.4: Please clarify the
extent of "all Fort Sam Houston ITBC controlled systems." The SOW
identifies sufficient detail for these systems. A more specific
question is needed if more specific information is sought. Question 50.
Para 2.2.7: Will the Government provide the space and GFE for training?
The Government expects the contractor to propose a training strategy
with assumptions, if appropriate. Question 51. Para 2.2.7: How many
training classes need to be conducted for each type of training? How
many people need to be trained for each type of training? The
Government expects the contractor to propose a training strategy
consistent with their technical solution. The Government expects X to
Y individual will require each type of training. Question 52. Para
3.2.1: Are there any cache requirements for the servers? See Question
1, above, based on server utilization. Question 53. Para 3.2.1: What
are the requirements for the capacities of individual disk drives or
RAID drives? They must be able to back up the system without
interruption of service. Question 54. Para 4.2: How is "oversight"
defined? Is there a single point of contact with the authority to sign
off on acceptance? Oversight is monitoring contractor
activity/progress to ensure ITBC standards are maintained. The client
representative or alternate may sign acceptance. Question 55. Will
DIICOE be followed for server selection? To be addressed in the
planning process after award. Question 56. In the Description section,
bullet (e) suggests that Time & Materials for the proposal is
acceptable. Yet, the last paragraph of the document seems to say that
"A firm fixed-price definite quantity, definite delivery contract will
be awarded." Are we required to respond with a bid for Fixed Price or
are bids specifying Time and Materials acceptable? The Government is
soliciting a Firm Fixed Price proposal. Question 57. Will the
Government provide a single point of contact for the project? The SOW
identifies the Client Representative and alternates responsible for
this project. Question 58. We are hesitant to provide for fixed-priced
quotation without full knowledge about the client's environment.
Therefore, we would like to ask Government for extension with possible
pre-bid conference and site survey. The Government will allow an
extension to 3/15/99 and will also allow for a one day site survey and
pre bid conference. Please contact Joe Eason at 210-472-5050 to
schedule an appointment during the week of March 8-12, 1999. Question
59. We need to understand ITBC's definition of server consolidation,
i.e., is this a complete turnkey solution in moving applications from
approximately 100 existing servers into several new high performance
servers? See question #2. Question 60. If the answer to Question 58 is
affirmative, we need know the physical capacity of each server, the
applications on each server, and roles each of these servers play in
the enterprise. See question #1. Question 61. Is ITBC taking the
responsibility for all 2YK issues in this consolidation? Fort Sam will
be responsible for Y2K compliance only on existing equipment. Posted
03/05/99 (W-SN305679). (0064) Loren Data Corp. http://www.ld.com (SYN# 0047 19990309\D-0005.SOL)
D - Automatic Data Processing and Telecommunication Services Index Page
|
|