COMMERCE BUSINESS DAILY ISSUE OF MARCH 25,1999 PSA#2310U.S. Army Engineers District, Wilmington District, Corps of Engineers,
Attn: Sherrel Sholar-Jackson, P.O. Box 1890, Wilmington, NC
28402-1890 Y -- FLOOD DAMAGE REDUCTION, CLINTON WASTEWATER TREATMENT PLANT,
CLINTON, NORTH CAROLINA SOL DACW54-99-B-0021 DUE 051399 POC Send checks
to: Oweita Freemen/CESAW-TS-EE (910-251-4741); Contract Specialist:
Hilda Ayers Work consists of construction of a new earth dike around a
portion of the wastewater treatment plant, excavation of two sump
areas, installation of a pumping station, construction of an access
ramp over the dike, and fence relocation and construction. Work must be
completed within 265 calendar days after contractor receipt of Notice
to Proceed. Estimated cost range for this project is $250,000-$500,000.
Advertising date is scheduled for 13 April 1999 with bid opening on or
about 13 May 1999. Plans and specifications are $46.00 per set and
will be available on or about 13 April 1999. Specifications only are
$34.00 each. Make checks or money orders payable to:"FAO,
USAED,WILMINGTON" and mail to address shown above, "ATTN: OWEITA
FREEMAN", or Express Mail to: 69 DARLINGTON AVENUE, WILMINGTON, NC
28403. No refunds will be made and material need not be returned. THIS
IS A 100% SMALL BUSINESS SET ASIDE. SIC CODE: 1629. Posted 03/23/99
(W-SN311391). (0082) Loren Data Corp. http://www.ld.com (SYN# 0147 19990325\Y-0009.SOL)
Y - Construction of Structures and Facilities Index Page
|
|