COMMERCE BUSINESS DAILY ISSUE OF APRIL 21,1999 PSA#2329Department of Veterans Affairs, Great Lakes Healthcare Systems, Great
Lakes Acquisition Center, Bldg. 5, 5000 West National Ave., Milwaukee,
WI 53295 Z -- REMOVE ABANDONED WELL & UPGRADE ANIMAL RESEARCH FACILITY SOL IFB
69D-259-99 DUE 060899 POC LAURA SILGUERO, Contracting Officer,
(414)902-5412 Provide all labor, materials, tools, equipment, and
qualified supervision to Remove Abandoned Well and Upgrade Animal
Research at the VA Hospital, Hines, Illinois, in accordance with
drawings and specifications. 1. Well Abandonment (Building 5) A
abandoned well in the boiler plant building will be removed according
to EPA guidelines. The well pump and casing will be removed through a
roof access hatch. 2. Animal Research Facility Upgrade (Building 1, 4th
floor, B-Section) The animal research facility upgrades include a new
epoxy resinous flooring, a new gypsum board ceiling with an epoxy
paint, and water resistant light fixtures. Completion time is 60
calendar days from the notice to proceed. Cost range is $250,000 --
$500,000. Project Engineer is Hayward Collins (708) 202-8387, ext
21152. Issue date is on or about May 7, 1999. Award is subject to the
availability of funds. SIC 1542 applies. There will be a nonrefundable
charge of $25.00 for the solicitation package. Make check payable to
the DEPARTMENT OF VETERANS AFFAIRS, and mail to Great Lakes Acquisition
Center, Attn: Marilyn Smith, 5000 West National Avenue, Building 5,
Milwaukee WI 53295-0005. Requests for solicitation must be submitted in
writing. No telephone requests will be accepted.****** Posted 04/19/99
(W-SN321780). (0109) Loren Data Corp. http://www.ld.com (SYN# 0139 19990421\Z-0015.SOL)