COMMERCE BUSINESS DAILY ISSUE OF APRIL 27,1999 PSA#2333USDA, Forest Service, SW Idaho/Nevada Acquisition Office, 1249 S.
Vinnell Way, Boise, ID 83709 Y -- UPPER PAYETTE LAKE CULVERT REPLACEMENT ON THE PAYETTE NATIONAL
FOREST SOL RFQ 12QR4-065-99 DUE 052599 POC Cheryl R. Molis, Contracting
Officer, 208-373-4131; Request for Solicitation, Ethel Hill,
208-373-4128 E-MAIL: To request solicitation, ehill/r4_boise@fs.fed.us.
The project will include procurement and construction of a 2438 mm span
x 1270 mm x 12.8 m corrugated steel arch pipe. Contractor will need to
procure all materials needed to construct the pipe including concrete
head walls and footers associated with the structure. Work will
consist of excavation, riprap placement, diversion of water during
construction, backfill in accordance with specifications, testing and
quantity measurement, salvage of existing culvert and transportation of
culverts on site to Government stockpile, and resurfacing of disturbed
road surface. The project is located northeast of FH 21 (Warren Wagon
Road) approx. 14 miles to the junction with FDR 50495, then north on
FDR 50495 for 1.2 miles to the Camp Creek Crossing located past the
entrance to Upper Payette Lake Campground. Est. start date is 9/13/99
with 25 calendar days for completion. The est. price range is between
$25,000 and $100,000. This proposed procurement is under the Small
Business Competitiveness Demonstration Program. Posted 04/23/99
(W-SN323961). (0113) Loren Data Corp. http://www.ld.com (SYN# 0093 19990427\Y-0008.SOL)
Y - Construction of Structures and Facilities Index Page
|
|