COMMERCE BUSINESS DAILY ISSUE OF APRIL 28,1999 PSA#2334USDA Forest Service, 2222 West 2300 South, Salt Lake City, Utah 84119 Y -- OGDEN VALLEY PAVING PROJECT ON THE WASATCH-CACHE NATIONAL FOREST
SOL ifb-19-99-043 DUE 062899 POC Contact Nelda Montgomery,
801/975-3443/ Contracting Officer Karen Goodsell, 801/975-3442 WEB:
nmontgom/wo_gsc@fs.fed.us, nmontgom/wo_gsc@fs.fed.us. This project is
for the placing of crushed aggregate base material and the paving of
roads and parking areas within the Huntsville Work Center Complex,
reconstruction of the entryway road into Port Boat Ramp with base and
paving, construction of a fisherman's access road, and parking facility
at Spring Crk. on Pineview Reservoir, mainly placing crushed surfacing
material plus paving 75 feet in from the Hwy. plus paving only 50-75
feet of approach road each at Willows CG, Botts CG, and two approaches
at Magpie CG. Magpie CG also includes paving a small parking area. All
paved areas including striping. The Huntsville Work Center Complex is
located just to the west in Huntsville, Utah (on the east side of
Pineview Reservoir) and is approx. 7 miles from the Jct. of State Hwy.
39 and the road which crosses the dam at Pineview Reservoir. Port Boat
Ramp is located on the road which crosses the dam and is just under 2
miles from the above mentioned Hwy. Junction. Spring Crk. Fisherman's
access is very near Huntsville at the NE corner of Pineview Reservoir.
The campground approach roads are all in Ogden Canyon and are 5-7
miles from Huntsville, Utah on State Hwy. 39. Estimated issue date
5/20/99. This procurement is estimated between $100,000 and $250,000.
Plans will be available at a $15 non-refundable charge. Solicitation
may be ordered by fax (801)975-3478 or in writing to the above
address.***** Posted 04/26/99 (W-SN324321). (0116) Loren Data Corp. http://www.ld.com (SYN# 0101 19990428\Y-0004.SOL)
Y - Construction of Structures and Facilities Index Page
|
|