COMMERCE BUSINESS DAILY ISSUE OF MAY 7,1999 PSA#2341U. S. Army Engineer District, Savannah, P.O. Box 889, Savannah, Georgia
31402-0889 Y -- IDIQ CONTRACT FOR CONSTRUCTION W/TIME AND MATERIALS CAPABILITIES,
FORT BRAGG, NC SOL DACA21-99-B-0033 POC Mr. Warren T. Clarke,
912-652-5163 (Technical Questions); Ms. Linda Elliott, 912-652-5076
(Contractual Questions) WEB: Corps of Engineers, Savannah District,
Contracting, http://www.usace.army.mil. E-MAIL: Linda G. Elliott,
linda.g.elliott@sas02.usace.army.mil. This will be an indefinite
quantity, multi-task construction contract with fixed labor rates for
a wide variety of maintenance, repair, and minor new construction
tasks. Work will be performed at (or in the vicinity of) Fort Bragg,
North Carolina or Reserve Centers in North Carolina. The contract is to
provide expeditious execution of task orders for general construction
or remediation of real property type work, which will vary from site to
site. The Contracting Officer will issue specific task orders in
accordance with the unit price schedule and task order specifications.
Contract duration will be an initial 12-month period with options for
two additional 12-month periods to be executed at the discretion of
the Government. The ordering period will be for 1 year or whenever the
Contracting Officer determines the ordering period is over and any
dollar amount not consumed by task orders issued during the ordering
period may be carried over to the next ordering period. The maximum
estimated contract amount for the base period and for each additional
12-month period is $7,000,000. Task orders will not be issued for less
than $2,500 or more than $500,000. The contractor will not be required
to accept more than a (cumulative) total of $2,000.000 in task orders
at any given time. The Government will obligate to the Contractor a
minimum of $140,000 for the base period and $70,000 for each option
period as the options are exercised. The Contractor will be required to
furnish all plant, labor, materials, permits, equipment, personnel, and
services necessary to manage and accomplish designated deliveries which
will include surveying the problem, recommending a solution, and
remediating the problem in a timely and efficient manner. Task orders
will include a variety of trades including (but not limited to)
biologist, environmentalist, environmental abatement (asbestos and
lead-based paint) technicians, agronomist, computer specialist,
carpentry, plumbing, road repair, roofing, excavation, demolition,
concrete, topographic surveyors, roofers, masonry, welding and
engineering (general, civil, mechanical, electrical structural, fire
protection, and/or safety). Contractors must have a minimum of 3 years
related experience and must possess all state and locally required
licenses for this type work within the areas specified in the
solicitation. Estimated cost range of this project is $10,000,000.00 to
$25,000,000.00. Requirement for Network Analysis System will be
determined for each task order. THIS SOLICITATION IS ISSUED ON AN
UNRESTRICTED BASIS PURSUANT TO THE "BUSINESS OPPORTUNITY DEVELOPMENT
REFORM ACT OF 1988" (Public Law 100-656). THIS SOLICITATION WILL BE
AVAILABLE ON OR ABOUT JUNE 1, 1999, ON THE INTERNET AT
http://www.sas.usace.army.mil/ebs/. NOTE: ALL REQUESTS FOR SOLICITATION
MUST BE MADE IN WRITING AND RECEIVED NOT LATER THAN 05/21/99. A LIMITED
NUMBER OF SOLICITATIONS WILL BE PREPARED AND ISSUED ON A FIRST COME
FIRST SERVED BASIS. THE NUMBER OF SOLICITATIONS WILL BE LIMITED TO ONE
(1) PER FIRM. STATE AREA CODE,TELEPHONE NUMBER, STREET ADDRESS AND
NINE-DIGIT ZIP CODE IN REQUESTS. REQUESTS MAY BE FAXED TO 912-652-5828.
PLANS AND SPECIFICAGIONS ARE AVAILABLE MONDAY THROUGH FRIDAY 8:30 A.M.
TO 5 P.M., 100 WEST OGLETHORPE AVENUE, SAVANNAH GA 31401-3640 Posted
05/05/99 (W-SN327876). (0125) Loren Data Corp. http://www.ld.com (SYN# 0232 19990507\Y-0026.SOL)
Y - Construction of Structures and Facilities Index Page
|
|