COMMERCE BUSINESS DAILY ISSUE OF MAY 21,1999 PSA#2351U.S. Army CECOM, CECOM Acquisition Center, Fort Monmouth, NJ
07703-5008 61 -- 100 AND 200 KW TACTICAL QUIET GENERATORS SOL DAAB07-99-R-B404
DUE 072399 POC Christopher Blumberg, 732-427-1668, Sharon Wilson,
732-532-4964 WEB: CECOM Acquisition Center's Business Opportunities
Page, http://abop.monmouth.army.mil. E-MAIL: Contract Specialist email,
blumberg@mail1.monmouth.army.mil. This program incorporates a
multi-phase strategy for procuring the 100 kW and 200 kW Tactical Quiet
Generator (TQG) sets. The phases are: Phase I, Engineering and
Manufacturing Development (EMD) (15 months), Phase II Option Continued
EMD (21 months) and Phase III Option Full Scale Production (10 years).
In the solicitation, offerors will be required to submit Technical,
Logistical, Performance Risk, Small Business and Small Disadvantaged
Business Participation Plan, and Cost/Price proposals. Based on these
proposals, one or more contractor(s) will be selected on a "best value"
basis and awarded an Indefinite Delivery Indefinite Quantity contract
to enter Phase I EMD (Cost Plus Fixed Fee) with options for Phases II
and III. The contractor(s) selected to participate in Phase I will
develop and deliver two(2) 100kW, 50/60 Hz (one skid and one trailer
mounted) and two (2) 200kW, 50/60 Hz prototype generator sets (one skid
and one trailer mounted). The contractor(s) will configure one unit of
both size generator sets onto government furnished equipment (GFE)
trailers in support of Phase I testing. These models will be tested per
the Purchase Description (PD). In the case of a multiple contract award
in Phase I, the government will assess the Phase I performance and
exercise the Phase II option to the "best value" contractor. The
evaluation criteria will consider test results from Phase I, revised
technical and logistics proposals for Phases II and III, and if
necessary, the revised cost/price proposals for Phase II and Phase III.
Phase II (Engineering and Manufacturing Development) will be a Cost
Plus Fixed Fee relationship to fabricate twelve (12) 100kW sets and
twelve (12) 200kW sets which will undergo Pre-Production Qualification
Testing (PPQT) by the contractor and the government. During this phase
two (2) 100kW, two (2) 200kW sets, and four (4) refurbished Phase I
prototypes will also undergo government operational testing (OT). Phase
II sets will also be used to conduct the Pre-Production Physical
Configuration Audit and Logistics Demonstration. Phase II culminates in
the successful completion of the PPQT. A Phase III option may be
awarded to the Phase II contractor upon successful completion of Phase
II testing. Phase III will authorize production requirements within a
ten year ordering period. Phase III will be a Firm Fixed Price (FFP)
relationship with an Economic Price Adjustment (EPA) starting on the
fourth year. Delivery will be from FY03 through FY13. The total "fleet"
requirement for DoD is approximately 784 100kW sets and 389 200kW sets.
Only offerors possessing SECRET Clearance may receive classified
portions of the RFP, submit proposals, or become eligible for contract
award. The U.S. Army Communications Electronics Command (CECOM) has
established a Business Opportunities Page (BOP) website to allow
electronic transmittal of Requests for Proposals (RFPs) and Invitation
for Bids (IFBs) from CECOM to Industry and proposals from Industry to
CECOM. All parties interested in doing business with CECOM are invited
to access, operate, send and receive information from the Business
Opportunity Page at (http://abop.monmouth.army.mil). Posted 05/19/99
(W-SN333347). (0139) Loren Data Corp. http://www.ld.com (SYN# 0274 19990521\61-0002.SOL)