COMMERCE BUSINESS DAILY ISSUE OF JUNE 14,1999 PSA#236692d Contracting Squadron W. 110 Ent St. (Suite 200), Fairchild AFB, WA
99011-9403 Z -- REVITALIZE EXTERIORS, FAIRCHILD AFB GYM AND BOWLING CENTER SOL
F45613 99 R0010 DUE 080999 POC Contract Administrator, MSgt Douglas
Guldan, (509) 247-4866; Contracting Officer, Barbara Hicks, (509)
247-4867 WEB: Electronic Procurement System Website, www.eps.gov.
E-MAIL: Click here to contact the contract administrator,
douglas.guldan@fairchild.af.mil. The objective of this project is to
revitalize the exterior of buildings 2248 (Bowling Center) and 2249
(Base Gym), at Fairchild AFB, WA. The work includes, but is not limited
to the complete removal of existing site asphalt and miscellaneous
concrete paving; continuous saw cutting and removal of the entire
existing loading dock and related concrete stairs, ramps, removal of
existing lap siding and metal fascia. Civil work includes new site
grading, removal and connections to existing storm, drain and fire
hydrant systems; new concrete curbs, gutters, asphalt and concrete
paving; poured in place and modular concrete retaining walls, site
earthwork, landscaping and irrigation. A thin brick and face brick
veneer shall be provided with a new continuous manufactured wall panel
fascia. Entry canopies shall be provided containing structural steel
and a metal roof system. Existing doors windows and frames shall be
provided with vehicle and pedestrian ramps, stairs, and levelers.
Electrical work includes new site and building mounted lighting and
concealment of existing electrical and communications lines. Mechanical
work includes relocation of various grilles and exterior HVAC
equipment. This acquisition will use Best Value, Past Performance
procedures. The magnitude of this project is estimated to be between $5
million and $10 million. Performance period for this project is 365
calendar days. This time period is further broken out into four
separate phases. The first phase is 60 calendar days for submittals;
the second through fourth phases (305 days), are for the contractor to
complete the physical portions of the work. A separate Notices to
Proceed will be issued for each phase. Work hours are 7:30 AM 4:30 PM
excluding federal holidays. This work is not located in a restricted or
controlled area. This project is 100% unrestricted. Any responsible
source may submit a proposal. Estimated proposal issuance date is 08
Jul 99. Interested parties may download the solicitation package from
www.eps.gov. This SIC Code for this acquisition is 1542. The business
size standard is $17 million. The project will have four line items.
The Base Items will consist of two line items for the Base Gym. Two
Optional Line Items will be for the combination of the Base Gym and the
Bowling Center. Award will be based on the amount of funding received.
SPECIAL STRADDLE BID: FUNDS ARE NOT PRESENTLY AVAILABLE FOR THIS
PROJECT. NO AWARD WILL BE MADE UNDER THIS SOLICITATION UNTIL FUNDS ARE
AVAILABLE. THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS
SOLICITATION EITHER BEFORE OR AFTER THE CLOSING DATE. Posted 06/10/99
(W-SN341719). (0161) Loren Data Corp. http://www.ld.com (SYN# 0153 19990614\Z-0004.SOL)