COMMERCE BUSINESS DAILY ISSUE OF JUNE 16,1999 PSA#2368U.S. Army Corps of Engineers, Portland District, P.O. Box 2946,
Portland, OR 97208-2946 Y -- BONNEVILLE TURBINE INTAKE FISH RELEASE PIPES SOL DACW57-99-B-0003
DUE 072999 POC Glenn Nishida, 503/808-4604 Two complete and identical
installations in two adjacent turbine intake units are required. Each
system consists of the following: Furnish and install approximately 400
feet of 8 inch diameter pipe for fish passage. Pipe materials used
include epoxy lined seamless steel, PVC, and seamless stainless steel.
Piping system includes sweeping bent curves, valves, and accessories.
Furnish other small size non-epoxy lined steel pipe valves and
accessories. Fabricate and install a fish trough. Troughs are 7 x 3 x
4 feet. Fabricate brackets, supports, clamps and many other
miscellaneous items. All fabricated items are steel. Metalwork in
contact with the fish transport system is to be painted with epoxy
paint. Furnish and install airlines and controls for operating the
system. Furnish and install 15hp turbine pump and 1 hp submersible.
Install tailrace release system on the tailrace face of the dam using
divers. Electrical work consists of furnishing panels, breakers, a 2kva
transformer 480v -- 120v, switches, wiring, and appurtenances. The fish
troughs will be placed on the powerhouse intake deck. The piping will
be installed down through an intake gate slot and in the turbine scroll
case area. All piping is to be attached to brackets and supports
mounted to the concrete structure. All work will be done in the dry
except the tailrace release system which will be installed using dive
crews. The Contractor shall be required to commence site work under
this contract within 60 calendar days after receipt of Notice to
Proceed and shall complete installation work no later than 25 October
1999. The Contractor shall be required to remove the Contractor
installed equipment during a Government approved period in the month of
February 2000. An optional bid item includes the reinstallation of the
equipment in October 2000 and its removal in January 2001. IFB will be
issued on CDROM on or about 29 June 1999, which may be obtained by
faxing a request to 503/808-4605 (ATTN: Kathy Seitz). Include you
business size, address, phone and fax numbers. Tentative bid opening
date is 29 July 1999. Estimated cost range is $500,000 to $1,000,000.
Procurement is 100% set aside for small businesses. The small business
size standard is average annual receipts for the previous three fiscal
years must not exceed $17,000,000. All responsible sources may submit
an offer which may be considered. Technical questions should be
directed to Ronald Wridge, 503/808-4927. SIC 1629 ***** Posted 06/14/99
(W-SN342435). (0165) Loren Data Corp. http://www.ld.com (SYN# 0134 19990616\Y-0015.SOL)
Y - Construction of Structures and Facilities Index Page
|
|