COMMERCE BUSINESS DAILY ISSUE OF JUNE 24,1999 PSA#2374IDAWY Contracting Center USFS, Federal Building -- Room101, 250 South
Fourth Avenue, Pocatello, ID 83201 Y -- LUDWIG BRIDGE REPLACEMENT, SALMON & CHALLIS NATIONAL FORESTS SOL
IDAWY-56-99 DUE 071599 POC Tammy Smith, 208-236-7584 This project
includes removal & disposal of an existing log bridge and installation
of a new precast concrete bridge or an approved equivalent. Project is
located on the Salmon & Challis National Forests, approximately 35
miles from Salmon, Idaho. Estimated start work date is August 1, 1999,
with a completion time of 30 days. Cost estimate is between $100,000
nad $250,000. FAX requests for bid package to 208-236-7503. Posted
06/22/99 (W-SN345690). (0173) Loren Data Corp. http://www.ld.com (SYN# 0124 19990624\Y-0023.SOL)