COMMERCE BUSINESS DAILY ISSUE OF AUGUST 11,1999 PSA#2407USDA Forest Service, Mt. Hood National Forest, 16400 Champion Way,
Sandy, OR 97055 Y -- PIONEER BRIDLE TAIL RESTORATION AND SANDY RIVER TRAIL RESTORATION
SOL R6-6-99-173 DUE 091899 POC Michael Patterson, Contracting Officer
(503) 668-1739, Roger Bell, Contracting, (503) 668-1739 WEB: GPO
341093, http://www.fs.fed.us/r6/mthood/noca. E-MAIL: Pioneer Bridle
Trail Restoration and Sandy River Trail, mpatterson@us.gov. URL
http://www.fs.fed.us/r6/mthood/noca 1. PIONEER BRIDLE TRAIL
RESTORATION: Reconstruction of trail to original grades and alignment,
i.e., removing rocks and roots, filling ruts and troughts,
reconstruction of ditches and other drainage structures. Restore a 1093
meter segment of existing trail and construct two (2) relocations (693
meter and 227 meter), and hauling and blasting. Estimate of cost of
these two (2) trails is between $50,000 and $100,000. Recommended
Contract Time is 270 Calendar Days. Desired Start Work Date is
September 30, 1999. 2. SANDY RIVER TRAIL RESTORATION; Restore two (2)
portions of trail 3727 meters and 322 meters. Construct 397 meter
relocation of trail and restore 301 meter portion of the spur to Ramona
Falls Trail Parking Lot. Construction work includes: clearing and
grubbing, excavation, shape and finish trailbed, back slopes, drainage
structures and blasting may be required. SIC Code for this project is
1611. This is a Small Business Set-Aside. Posted 08/09/99
(W-SN365332). (0221) Loren Data Corp. http://www.ld.com (SYN# 0118 19990811\Y-0015.SOL)
Y - Construction of Structures and Facilities Index Page
|
|