COMMERCE BUSINESS DAILY ISSUE OF SEPTEMBER 7,1999 PSA#2426100 Kindel Drive, Suite A332 Arnold AFB TN, 37389-1332 59 -- PROVIDE 480-VOLT SECONDARY SWITCHGEAR SOL F40650-99-Q-0024 DUE
092199 POC Tony Clayborne,(931) 454-3918 WEB: 99Q0024-Provide 480-volt
secondary switchgear,
http://www.pixs.wpafb.af.mil/pixslibr/99Q0024/99Q0024.asp. E-MAIL:
Tony.Clayborne@arnold.af.mil, Tony.Clayborne@arnold.af.mil. This
requirement is for the design, manufacture, assembly, and delivery of
a 480-volt secondary switchgear for an existing 1500 kilovolt-ampere,
secondary unit substation to replace the existing forty-four year old
secondary switchgear. The performance period shall be 180 calendar days
after contractor receipt of written notification of contract award. Any
responsible source may submit a quote which shall be omsidered. Firms
responding to this synopsis should indicate wheter or not they are a
minority business concern. Foreign participation is authorized. Quotes
will be due 14 calendar days after issuance of the Request for Quote.
The aniticpated due date is estimated to be 21 September 1999. Posted
09/02/99 (D-SN375893). (0245) Loren Data Corp. http://www.ld.com (SYN# 0338 19990907\59-0012.SOL)
59 - Electrical and Electronic Equipment Components Index Page
|
|