|
COMMERCE BUSINESS DAILY ISSUE OF OCTOBER 1,1999 PSA#2445Federal Aviation Administration, 601 E. 12th St., ACE-55, Room 1524,
Kansas City, MO 64106 Y -- LIGHTNING PROTECTION UPGRADE AT LAMBERT-ST. LOUIS INTERNATIONAL
AIRPORT, ST. LOUIS, MO SOL DTFA09-00-R-20010 DUE 102999 POC Jim Barnett
(jim.barnett@faa.gov) WEB: FAA Central Region Procurement
Announcements, http://www.tc.faa.gov/cen/ace-55-2.htm. E-MAIL:
DTFA09-00-20010, jim.barnett@faa.gov. SOURCES SOUGHT. The Federal
Aviation Administration, Central Region, is seeking sources to provide
Lightning Protection Upgrade,at Lambert-St. Louis International
Airport, St. Louis, MO. GENERAL SCOPE OF WORK: Replace all existing
bolted connections on the lightning protection system with
exothermically welded connections. This will include approximately 69
connections at the CAB and SUBJUNCTION levels, 16 connection to air
terminals at the CAB and SUB-JUNCTION levels, and 32 air
terminals/bonds at the BB roof level for an approximate total of 117
exothermic welds. Some locations may also require extension of the
roof/down conductor length to allow room for the mold. All new
construction shall be installed in accordance with NPFA 780 and FAA
specifications. SPECIAL CONSIDERATIONS: It will be necessary for the
contractor to schedule and plan all work, and coordinate with the COR,
so that normal airport and FAA facility operations may continue. The
Air Traffic Control Tower and Base Building operations are 24 hours a
day seven days a week. Additional coordination with the airport
authority and airlines may be required for locating equipment (crane)
or other equipment at the base of the tower. The Air Traffic Control
Tower is approximately 215 feet tall and due to its structure will
require the use of special rigging to perform the required exothermic
welding, bonding, and mounting of the lightning protection components.
It will be feasible to use a crane for portions of this work, but
access to all locations may not be possible due to the building layouts
and equipment on the ground. Estimated total cost is between $50,000
and $75,000. Schedule: The FAA plans to start work on this project in
late 1999 with completion in early 2000. Responses/questions should be
addressed to Jim Barnett @ jim.barnett@faa.gov This announcement is
not an RFP. Posted 09/29/99 (W-SN386337). (0272) Loren Data Corp. http://www.ld.com (SYN# 0104 19991001\Y-0014.SOL)
Y - Construction of Structures and Facilities Index Page
|
|