Loren Data Corp.

'

 
 

COMMERCE BUSINESS DAILY ISSUE OF NOVEMBER 16,1999 PSA#2476

Department of the Army and Air Force, NGB, USPFO for Maine, Camp Keyes, Augusta, Maine 04333-0032

Y -- CONSTRUCTION OF A BASE FIRE STATION AT BANGOR INTERNATIONAL AIRPORT (ANG), BANGOR, MAINE SOL F101DX-9014-0100 POC Contracting Officer, MSG Stephen E. Moody at 207-626-4354 (Site Code: DAHA17) WEB: Contracting Officer for this project, moodyse@me-arng.ngb.army.mil. E-MAIL: Contracting Officer via e-mail, moodyse@me-arng.ngb.army.mil. DESC: The Maine National Guard is interested in finding sources interested in the following project. This is a 100% Small Business Set-Aside. The successful contractor will furnish all material, equipment and labor associated with the construction of a Base Fire Station at Bangor International Airport (ANG), Bangor, Maine The issuing invitation to bid on or about the 4th of January 2000, the bid opening date and time is schedule for 1 February 2000 at 1:00pm local time. Project completion date is 365 days after the issuance of a Notice to Proceed. Furnishing all plant, tools, equipment, material supplies, and manufactured articles; furnishing all transportation and services, including fuel, power, water, and essential communications; performance of all labor, work, or other operations required for fulfillment of the contract in strict accordance with the specifications, drawings, and other contract documents. The size is approximately 14,400 square feet as calculated by Maine Air National Guard Standard. The actual dimensions are Ground floor footprint = 8,350 square feet, Second floor footprint = 8,000 square feet (of which 525 sf is an open deck) This gives a total enclosed space area of approximately 15,850 square feet. Building height is approximately 35 feet (the second floor is 20 feet above the first floor) Construction: Steel frame open web steel joists and steel beams for roof with composite steel beams for the floor; 8" exterior steel stud with corrugated prefinished metal siding over most areas with one area covered with standing seam prefinished roof and walls and one area covered in flat seam metal siding; cmu partitions and drywall on metal stud on first floor; drywall on metal stud partitions on second floor; ground floor is concrete slab on grade with a 2 foot high concrete curb above finished floor, and second floor is concrete on metal composite deck; roof is flat (except for single story area which is standing seam and low pitch) metal deck with 4-1/2" insulation; there are 14, 14'x14' overhead doors requiring steel framing (7 in front and 7 in back) and ribbon windows on the second floor which require steel framing as well; there are extensive exterior paved areas and earth work to accommodate the fire trucks for drive through capability and parking and lighting; demolition of existing fire station may be an additive bid item as well as the landscaping over that portion of the site. Electrical System: Main building service is 600 amps at 120/208 volts, 3 phase, 4 wire, matching existing fire station voltage and a separate 120/208 volt service to feed non-essential loads; a complete building ground loop; fire alarm system is fully automatic and is comprised of smoke detectors, heat detectors, pull stations, audio visual devices, etc.; there is a public address system and security system; there is a cable tray system for data wiring; there is an approximately 70 foot high radio tower and antenna; there are extensive electrical systems required to interface and operate the various warning systems and overhead doors; there are computer cables as well as base communication systems; there is a generator to be located adjacent to the building with 2 transfer switches, one for life safety systems and one for non-emergency loads; the building lighting is controlled by various sources including low voltage control systems, the direct digital control system via contractors, and local control; the exterior lighting is high pressure sodium. Plumbing System: There are 4 water closets and 6 bathrooms; the building is fully sprinkled; there is hot water from a boiler; there is an air compressor and piping; there is a foam tank system with pumps to fill foam truck; there are fill valves at each vehicle bay. Mechanical System: The building is heated and air conditioned with a package rooftop air conditioning unit, a duct mounted preheat coil and terminal v.a.v. boxes with reheat coils. Perimeter baseboard radiation is used as supplemental heat. An oil fired cast iron hot water boiler with a tankless coil provides heating and domestic hot water. The vehicle bays are heated by hot water unit heaters. An existing vehicle exhaust system is being relocated from the existing base fire station and modified/expanded to accommodate the new layout. A direct digital control system provides environmental control. Estimated cost is between $1,000,000 to $5,000,000. SIC Code: 1542. This is a Small Business Set-Aside. Number Notes 1: The proposed contract is 100% set-aside for small business concerns. Posted 11/12/99 (W-SN400207). (0316)

Loren Data Corp. http://www.ld.com (SYN# 0112 19991116\Y-0005.SOL)


Y - Construction of Structures and Facilities Index Page