COMMERCE BUSINESS DAILY ISSUE OF JANUARY 19,2000 PSA#2518Department of the Army, Memphis District, Corps of Engineers, 167 N
Main St, Rm B202, Attn: CEMVM-CT, Memphis, TN 38103-1894 Y -- MARKET SURVEY FOR DUSTPAN DREDGE IN 2000 POC POC: Tom Morgan
(901) 544-3114 WEB: Memphis District Corps of Engineers,
http://www.mvm.usace.army.mil. This notice is to conduct a market
survey for acquisition planning to ascertain whether qualified sources
with the required equipment capable of satisfying the government's
requirements exist (FAR 7.101). The purpose of the survey is to locate
sources with the required equipment interested in receiving a
solicitation, should one be issued, for lease of one dustpan hydraulic
pipeline dredge, fully operated with attendant plant, to perform
dredging operations in the Mississippi River at designated locations,
primarily between Memphis, TN (Mississippi River Mile 735 AHP) and the
Gulf of Mexico (Mississippi River Mile 18.8 BHP). The dredge shall be
not less than 38 inches diameter discharge and not less than 3600 pump
brake horsepower rating for continuous operation. The rate of advance
of the dredge, which is the forward movement of the dredge while
pumping materials, shall be the rate required to maintain the minimum
production rate. The discharge size will be considered to be the
minimum diameter of either the pump discharge or discharge line,
whichever is the lesser. The suction pipe shall have an intake section
of pipe with valve near the pump for the purpose of inserting dye in
the pump to determine the velocity. The dredge shall be capable of
starting work and working efficiently in 10' depth. The depth of
dredging generally ranges from 12' to 60'. The draft of the dredge
shall not exceed nine feet. The dredge shall be of such design as to
work efficiently and permit passage of other vessels while working in
a 300 to 500 foot wide channel. The dredge shall be adequately powered
and properly equipped for the pump size and horsepower used. The
minimum estimated dredge output shall be 4800 cubic yards per pumping
hour. Attendant plant shall consist of (1) derrick (self-propelled),
(2) derrick barge ("A" frame), (3) floating pipeline (1000 foot), (4)
two tenders, (5) one workboat. This is not a formal solicitation.
Concerns that respond must furnish detailed information concerning the
required equipment andtheir capabilities NLT 03 February 2000. Point
of contact is Tom Morgan at (901) 544-3114. Posted 01/14/00
(W-SN416353). (0014) Loren Data Corp. http://www.ld.com (SYN# 0125 20000119\Y-0010.SOL)
Y - Construction of Structures and Facilities Index Page
|
|