COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 7,2000 PSA#2531USA Materiel Command Acqiuisition Center, Yuma Proving Ground Contracts
Division, ATTN: AMSSB-ACY/Bldg. 2100, Yuma, AZ 85365-9106 56 -- 20,410 LINEAL FEET OF CAIN LINK FENCING SOL W81R8T-00240PW67 DUE
022200 POC POC Thomas E. Nabozny, Contract Administrator -- phone
520-328-6354 of facsimile 520-328-6534 E-MAIL:
Thomas.Nabozny@yuma-exch1.army.mil, Thomas.Nabozny@yuma-exch1.army.mil.
This is a combined synopsis/solicitation for commercial items prepared
in accordance with the format in Subpart 12.6, as supplemented with
additional information included in this notice. This announcement
constitutes the only solicitation: proposals are being requested and a
written solicitation will not be issued. This order will be issued
under the Simplified Acquisition Procedures (SAP) as a 100% small
business set-aside. This solicitation document and incorporated
provisions and clauses are those in effect through Federal Acquisition
Circular (FAC) 97-11 (4 November 1999) Defense Acquisition Circular
(DAC) 91-13 (March 1998). The Standard Industrial Classification (SIC)
for this requirement is 3496 with a size standard of 500 employees.
The U.S. Army has a requirement for installation of approximately
20,410 lineal feet of chain link fencing six feet high above ground,
seven each pair ten foot wide Double Swing Gates (20 feet opening
width). The Installation site is located south of Tower 7 and Poleline
Road at Kofa Firing Range (KFR), U.S. Army Yuma Proving Ground. All
work shall be completed within eight weeks. An organized Site Visit has
been scheduled for February 15, 2000 at 9:00 a.m. Mountain Standard
time. Participants will meet at the Contracting Office, Room 8,
Building 2100, Material Test Directorate, Yuma Proving Ground, Arizona.
Drawings will be furnished at the site visit. STANDARD OF QUALITY The
fencing shall be of industrial manufacture, designed per the drawings
and the U.S. Army Corps of Engineers Standards for Security Fencing.
Work shall include nine gauge zinc coated chain link fence fabric with
two inch mesh six feet above grade, Tuff-40 steel fence posts with
caps and nine gauge galvanized top tension wire in lieu of top rail.
Fence shall be braced and trussed as needed. Fabric to be fastened to
line post with the tire wires spaced approximately 24 inches apart.
Gate frames are to be galvanized tubular pipe with mortised corner
joints for proper fit. Welds are to be continuous around pipe, cleaned
and treated with zinc-rich paint. Fabric to be same as fence. Gates
are to be complete with 180 degree socket hinges, industrial drop rod,
catch, stops and center rest flush with ground and concrete poured
around it. Concrete installed for fence posts footings shall be poured
above grade (mounted) approximately two inches at the post and sloped
to grade at the outer edge of the post hole for proper water drainage.
Work shall include all necessary hardware, nuts, bolts, screws,
fasteners, tension bars, top and bottom tension wires, tie wires, etc.
as required for complete installation. All fencing materials shall
have factory applied zinc coatings for a durable, non-rusting and
maintenance free installation. Fencing and gates, as constructed, shall
suit the intended purpose and be completed in a professional manner in
conformance with applicable trade practices. Upon completion, all
installation debris shall be cleaned up and removed from the site.
Contractor shall coordinate all work herein,in advance, with Pyramid
Services, Inc. at phone 328-2119. Prior to any welding or torch cutting
operations necessary, Contractor shall secure a Hot Work Permit from
Yuma Proving Ground Fire Department by phoning 328-2316. And cancelled
at the end of the working day. Prior to digging any holes or making
any excavations, the Contractor shall secure a copy of the required
Yuma Proving Ground Digging Permit from Pyramid Services, Inc. by
phoning 328-2119. Environmental Considerations: All products specified,
furnished and installed herein shall be free of Ozone Depleting
Components (ODC). The Contractor's quote shall consist of Contract Line
Item Number 0001 Furnish all Labor, Material, Transportation and
Equipment necessary to complete installation of approximately 20,410
lineal feet chain link fencing 6' high with 7 each 20' wide swing
gates, South of Tower 7 & Poleline Road, KFR Quantity -- 1 JOB. All
quotes shall be clearly marked with RFQ Number and submitted to the
Commander, U.S. Army Yuma ProvingGround, Office of Contracting, ATTN:
Mr. Thomas E. Nabozny, Room 8, Building 2100, Yuma, Arizona 85365-9106
no later than 11 a.m. Mountain Standard Time, February 22, 2000.
Applicable FAR clauses and provisions applicable to the resultant award
are as follows: 52.212-1 Instructions to Offerors Commercial Items (Nov
1999); 52.212-4 Contract Terms and Conditions Commercial Items (May
1999); 52.247-34 F.O.B. Destination (Nov 1991); 52.212-3 Offeror
Representations and Certifications Commercial Items (Oct 1999);
52.212-5 Contract Terms and Conditions Required to Implement Statutes
or Executive Orders Commercial Items (May 1999); 52.215-18 Facsimile
Proposals (Dec 1989); DFARS 252.212-7001 Contract Terms and Conditions
Required to Implement Statutes or Executive Orders Applicable to
Defense Acquisitions of Commercial Items (Sep 1999) and
HTTP://WWW.DTIC.DLA.MIL/AMC. SEE Note 1 Posted 02/03/00 (W-SN421427).
(0034) Loren Data Corp. http://www.ld.com (SYN# 0240 20000207\56-0001.SOL)
56 - Construction and Building Materials Index Page
|
|