|
COMMERCE BUSINESS DAILY ISSUE OF MARCH 2,2000 PSA#2548USACE Vicksburg District, 4155 Clay Street, Vicksburg, MS 39180-3435 C -- FIRM FIXED PRICE CONTRACT FOR THE PREPARATION OF DESIGN REPORT
AND PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF HOUMA NAVIGATION LOCK,
MORGANZA TO THE GULF OF MEXICO HURRICANE PROTECTION PROJECT, TERREBONNE
PARISH, LOUISIANA, NEW ORLEANS AND VICKSBURG DISTRICTS DUE 033100 POC
Laura Cespedes, 601-631-5575 WEB: Contracting Division Homepage,
http://www.MVK02.usace.army.mil/contract/. E-MAIL: Laura Cespedes 601
631-5575, Laura.Y.Cespedes@MVK02.usace.army.mil. CONTRACT INFORMATION:
Due March 31, 2000. POC Laura Cespedes, 601/631-5575, A-E services are
required for the preparation of a Design Report and Plans and
Specifications for the Houma Navigation Lock. One A-E contract as
described below will be awarded and administered in three phases. The
first phase of work is the design report, the second phase is an option
for the completion of the Plans & Specifications and the third phase is
an option for engineering services during construction. This
announcement is open to all businesses regardless of size. If a large
business is selected for this contract, it must comply with FAR
52.219-9 regarding the requirement for a subcontracting plan. The FY
2000 subcontracting goals for the Vicksburg District are: (1) at least
61.2 percent of a contractor's intended subcontract amount be placed
with small businesses (SB) including small disadvantaged businesses
(SDB), women-owned small business (WOSB) and HUBZone small business;
(2) at least 9.1 percent of a contractor's intended subcontract amount
be placed with SDB; (3) at least 5.0 percent of a contractor's
intended subcontract amount be placed with WOSB; and (4) at least 1.5
percent of a contractor's intended subcontract amount be placed with
HUBZone small business. Effective 14 June 1999, the small business size
standard for A-E services is 4.0 million. Subcontracting intentions are
outlined in Block 6 of SF 255. 2. PROJECT INFORMATION: The Lock will be
located in the Houma Navigation Canal (HNC) which is a man-made channel
constructed in 1961 that provides direct access to the Gulf of Mexico
from the Gulf Intracoastal Waterway at Houma, Louisiana. The lock will
be installed in the HNC approximately 3,000 feet south of its southern
intersection with Bayou Grand Caillou, in Terrebonne Parish, Louisiana.
This site is approximately 3.3 miles downstream of the LA Hwy 57
floating- bridge crossing at Dulac, Louisiana. The project consists of
a lock with two sets of sector gates, each with up to a maximum
200-foot-wide gate opening, mounted in a pile founded concrete gate
monolith. The center?to?center distance between the two gate monolith
structures could be up to 1,200 feet. The chamber will be earthen with
walls and gate monoliths. The project may require the design of bypass
channels, cofferdams, and site work. Innovative concepts such as
float-in concrete sector gate monoliths will be investigated during the
design report phase. The float-in monoliths could utilize lightweight
concrete that is pre-stressed or post-tensioned. Other ancillary
project features include sector gate operating machinery, electrical
service, roadways, utilities, buildings, floodwall tie ins, sheet pile
walls, guide walls, channels, levees, and other incidental work
required for constructing the lock. The A-E shall furnish all services,
materials, supplies, plant, labor, equipment, studies, investigations
(including geotechnical designs, surveys and mapping) supervision, and
travel as required to prepare the design report and plans and
specifications (including construction cost estimates) for the work
described above. The government will furnish geotechnical data.
Drawings and plates shall be prepared as required to present project
details and/or study results. All drawings shall be furnished in a
Microstation design file format. The Design Report and all text shall
be prepared in Microsoft Office 97 or later version. Phase 1 -- Houma
Navigation Lock Design Report. Work consists of data collection,
including surveys and other possible investigations, civil site work,
geotechnical, structural, mechanical and electrical design, cost
engineering and preparation of a design report for the lock. The Design
Report will present alternatives including construction of the gate
monoliths in place vs. off site construction of float-in gate
monoliths. The Design Report will include engineering and cost
comparison of alternatives, a presentation of design methodology,
construction cost estimates, narratives, plates, etc., Phase 2 -- Houma
Navigation Lock Plans and Specifications. The work consists of
finalizing the Design Report design and preparing plans and
specifications for construction of the Houma Navigation Lock with all
related features. Phase 3 -- Engineering Services During Construction.
The work consists of engineering services during construction such as
review of submittals, changes or resolution of problems, site visits,
etc. 3. SELECTION CRITERIA: The selection criteria are listed below in
descending order of importance; criteria (a) thru (e) are primary and
criteria (f) thru (h) are secondary and will be used only as
"tie-breakers" if necessary, in ranking the most highly qualified
firms. (a) Specialized experience and technical competence of the firm
and its key personnel to perform planning and design of steel
reinforced concrete structure projects similar in size and complexity
to a navigation lock, design of machinery, design of mechanical and
electrical systems for similar marine projects, geotechnical foundation
investigations and designs for large structures on soft foundations,
including subsurface exploration, pile analysis, foundation design in
areas of marsh alluvial geology including cofferdam and levee design,
experience in design of float-in and submerged concrete marine
structures, and hydraulic steel floodgates. (b) Professional
qualifications of the key design personnel available for work on this
project in the following disciplines: civil engineering, structural
engineering, marine engineering, naval architecture, architecture,
geology, geotechnical engineering, electrical engineering, mechanical
engineering, cost engineering, surveying experience using total station
data collection systems, and CADD. Expertise in developing GIS and
digital mapping products associated with this project in Intergraph
format. Expertise with MGE and GeoMedia environment using the SDSFIE
(a.k.a. TSSDS) spatial data standards. Expertise in development of WWW
Internet content to distribute and provide project design data,
images, multimedia, and Internet-based mapping/GIS data systems. (c)
Capacity in personnel and equipment to submit the designs and plans and
specifications for advertisement within the following time frame after
contract award: Design Report -- 300 calendar days, Plans and
Specifications -- 400 calendar days after completion of the Design
Report. The work in Phase 2, Plans and Specifications may be initiated
before the completion of Phase 1, Design Report. The prime contractor
and all sub-consultants must be capable of providing the following
minimum design personnel available to perform work on the above
contracts: 4 civil engineers, 8 structural engineers, 2 geotechnical
engineers, 1 hydraulic engineer, 1 marine engineer, 1 naval architect,
1 architect, 1 geologist, 1 electrical engineer, 1 mechanical
engineer, 1 cost engineer, 1 land surveyor registered in Louisiana, 6
CADD technicians, 1 GIS technician and 1-three person topographic
survey crew, (d) Knowledge of the local environmental conditions and
building codes for construction in a brackish marine environment.
Knowledge of the local alluvial geology and geography, (e). Past
performance on DOD and other contracts with respect to cost control,
quality of work and compliance with performance schedules, (f) Extent
of participation of small business, including small disadvantaged
business, historically black colleges and universities, and minority
institutions on the proposed contract team as measured as a percentage
of the total anticipated contract effort, regardless of whether the
SB, SDB, HBCU or MI is a prime contractor, subcontractor or joint
venture partner, the greater the participation, the greater the
consideration, (g) Volume of DoD contract awards in the last twelve
months and (h) Location of the design firm in the general geographic
area of the project. 4. SUBMISSION REQUIREMENTS: See Note 24 in
Monday's CBD for general submission requirements. Firms which meet the
requirements described in this announcement are invited to submit 5
completed copies of a SF 255 (11/92 edition) for the prime/sub and 5
completed copies of a SF 254 for the prime and each subcontractor and
consultant to the address below. In Block 10 of the SF 255, include an
organizational chart, the use of subcontractors or consultants and
provide an outline and description of the prime design firm's quality
control plan, including coordination of subcontractors and consultants.
Note the following restrictions on submittal of SF255. Block 7 --
Resumes of key persons, specialists, and individual consultants
anticipated for this project -- will be limited to a maximum of 20
pages. Block 10 -- Additional information -- will be limited to a
maximum of 20 pages. Pages in excess of the maximum of 20 will be
discarded and not used in evaluation of the selection criteria.
Information included in any cover letter will not be considered in the
evaluation. Include the firm's ACASS number in SF 255, Block 3. For
ACASS information, call (503) 808-4591. Overnight or courier type mail
should be sent to the following address: U.S. Army Corps of Engineers,
Vicksburg District, CEMVK-ED-CE, Attn: Laura Cespedes, 4155 East Clay
St., Vicksburg, MS 39183-3425. Solicitation packages are not provided.
This is not a request for proposal. VISITS FOR THE PURPOSE OF
DISCUSSING THIS ANNOUNCEMENT WILL NOT BE SCHEDULED. NOTE: Before an
award of a contract, as a result of this announcement, Contractors must
be registered in the Central Contractor Registration (CCR) database,
for information see http: www.crc.ctc.com Posted 02/25/00 (W-SN428739).
(0056) Loren Data Corp. http://www.ld.com (SYN# 0029 20000302\C-0004.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|