|
COMMERCE BUSINESS DAILY ISSUE OF MARCH 21,2000 PSA#2561Department of the Air Force, Air Education and Training Command, Luke
AFB Contracting Squadron, 14100 W. Eagle Street, Luke AFB, AZ, 85309 Z -- UPGRADE PRODUCT RECOVERY FACILITY SOL F02604-00-T0092 DUE 032900
POC Ken Miller, Contract Administrator, Phone 6238563442x255, Fax
6238563438, Email ken.miller@luke.af.mil -- Kurt Weilbaecher, Contract
Specialist, Phone 623)856-6353x231, Fax (623) 856-3447, Email WEB:
Visit this URL for the latest information about this,
http://www.eps.gov/cgi-bin/WebObjects/EPS?ACode=P&ProjID=F02604-00-T00
92&LocID=509. E-MAIL: Ken Miller, ken.miller@luke.af.mil. This is a
combined synopsis/solicitation for commercial items prepared in
accordance with the format in subpart 12.6 as supplemented with
additional information included in this notice. This announcement
constitutes the only solicitation; proposals are being requested and a
written solicitation will not be issued. This solicitation, No
F02604-00-T0092 is issued as a Request for Quotation (RFQ). Funds for
this acquisition are available. This solicitation document and
incorporated provisions and clauses are those in effect through Federal
Acquisition Circular 97-15. This acquisition is 100% set-aside for
HubZone small business. Contract Line Item(s): (CLIN) 0001; SCOPE: The
project covered by this statement of work consists in furnishing all
labor, equipment, and materials necessary to upgrade the 1,000-gallon
used oil aboveground storage tank AST (#887) and the recyclable JP-8
AST (#888) to meet 40 CFR 112.7 overfill protection requirements at the
Product Recovery Facility. AST# 888 is a double-wall steel tank
consisting of two 3,000-gallon separate tanks with a single-wall outer
shell. Repairs shall include the installation of an high/low level
product alarm system, design, electrical connection from high/low level
alarm system to automatically shut off transfer pumps when alarm
activates, and the installation of visual tank gauges. In addition, and
a permanent eye wash unit shall be connected to existing base utility
systems. A steel ladder with railing will be installed on the west end
of AST #888. USER: 56th Civil Engineer Squadron, Environmental
Programs Flight, Compliance Section (56 CES/CEVC). Telephone # (623)
856-3823 x225. The Environmental Flight POL Program Manager will serve
as the AF Project Manager. DESCRIPTION: The Contractor shall perform
the following tasks to complete this statement of work: 1.
Environmental Compliance Activities: The Contractor shall repair the
existing overfill alarm system or install a Veeder-Root (VR) overfill
alarm system or equal on AST nos. 887 and 888 (see Attachment 1).
Veeder-Root Specifications are: 1.1. VR Guardian AST Monitoring System
Item # 848590-110 -- 1 unit 1.2. VR Guardian High/Low Level Sensor
Item# 794390-Yxx -- 3 sensors 1.3. The Contractor shall mount the AST
Monitoring System Console in a fan-ventilated metal box to prevent
overheating during summer months. An example of an acceptable system is
located at building 1018. 1.4. The Contractor shall test the system to
ensure it is accurate and operational for all three ASTs. 1.5 The
Contractor shall wire the overfill alarm to the transfer pumps so that
the pumps will automatically stop when the overfill alarm activates.
2. Install Visual Tank Volume Gauges: The Contractor shall install one
Hersey Hydraulic Visual Gauge or equal (liquid volume in gallons) on
each of the three (3) ASTs. 3. Install Permanent Eyewash Unit: The
Contractor shall install a permanent eyewash unit equal to construction
and design to American Health & Safety Item # 2133021 Model W9332
w/foot pedal (See Attachment 2). 3.1 The Contractor shall connect the
permanent eyewash unit to the base_s water supply system. 4.
Construction Activities _ Ladder/Platform at AST #888: The Contractor
shall install steel ladder to hatchway at the west end of AST #888 and
on the north side of the tank. Ladder shall be constructed of steel
grating with dimensions of 2.5 to 3.0 feet in width and approximately
8 feet in height (similar to the existing ladder/platform on the south
end/west side of AST# 888). 4.1. Ladder will be welded securely to
tank and/or external framework. 4.2. Ladder shall be painted to match
ASTs in color and type. 5. Piping Supports: The Contractor shall
install metal piping supports on AST nos. 887 and 888. Two supports per
pipe for a total of eight (8) supports. The Contractor shall seal the
drilled holes in the concrete pad with JP-8 resistant silicone sealant.
6. SCHEDULE AND SUBMITTALS: The Contractor shall develop a schedule
which incorporates all critical work elements and submittals described
in the Statement of Work.Estimated time to complete this SOW is 6
months from receipt of the Notice to Proceed. 7. ITEMS AND DATA TO BE
FURNISHED BY THE GOVERNMENT: The AF Project Manager or his designee_
will coordinate site access and site layout to include any equipment
storage requirements. All required utilities clearances through 56 CES
(AF Form 103s) shall be obtained by CEVC. 8. DEVIATION FROM SCOPE OF
WORK: The Contractor shall not depart from nor perform work outside of
this Statement of Work and criteria on which the Statement of Work is
based without the written direction of the Contracting Officer (CO).
If the contractor performs such work without written approval, it does
so at its own risk. Any changes to this SOW will be coordinated with
56 CES/CEVC as well as the CO. 9. ACCEPTANCE OF WORK: The AF Project
Manager will approve and accept all work and submittals. 10. VISIT TO
SITE, PRIVATE SOURCES, AND GOVERNMENTAL AGENCIES: The Contractor shall
advise the AF Project Manager of each proposed visit to the site,
private sources, and government agencies (federal, state, county and
city) prior to each visit. 11. OTHER REQUIREMENTS: The Contractor shall
be a licensed contractor registered with the State of Arizona Registry
of Contractors. 12. The Contractor shall not enter into any
subcontracts that are not identified in its original proposal without
prior written approval of the CO. 13. An Manufacturer
Distributor/Authorized Service Provider must install overfill
protection alarm and monitoring equipment and submit to the
Manufacturer and 56 CES/CEVC, the manufacturer_s warranty documentation
for equipment installed. 14. RELEASE OF DATA: All data, reports, and
materials relative to this SOW are the property of the Government and
will not be released by the Contractor without written approval of the
CO. 15. RESPONSIBILITY FOR FIELD WORK: The Contractor shall be
responsible for all damages to persons and property that occur as a
result of the Contractor_s fault or negligence in connection with field
work, and shall save and holdthe Government free from all claims and
suits arising from such damage. This is a brand name or equal
requirement the FAR Clause 52.211-6 applies. Basis of award: award will
be made to the lowest-price Offeror, best demonstrating their ability
to satisfy the technical capabilities of the items specified. Offerors
of any equal must provide descriptive literature to this office for
evaluation. Required delivery: 30 days ARO. FOB: Destination to Luke
AFB, AZ. All prices shall include all Federal, State and Local taxes.
The following FAR & DFARS provisions and clause(s) applies to this
solicitation. FAR 52.212-1, Instructions to Offerors -- Commercial
Items, Far 52.212-4, Contract Terms and Conditions -- commercial Items,
FAR 52.212-5, Contract Terms and Conditions Required to Implement
Statutes or Executive Order -- Commercial Items with addenda
incorporating FAR clause(s) 52.222-26, Equal Opportunity; 52.222-35,
Affirmative Action for Special Disabled and Vietnam ERA Veterans;
52.222-36, Affirmative Action for Workers with Disabilities; 52.222-41;
DFARS 252.212-7001, Contract terms and Conditions Required to Implement
Statutes or executive orders Applicable to Defense Acquisitions of
Commercial Items with addenda incorporating DFARS clauses(s)
252.225-7001, Buy American Act and Balance of Payment Program, DFARS
252.204-7004 Required Central Contractor Registration (MAR 1998) (DFARS
204.7304). Offers shall be submitted in writing and received not later
than 4:30 PM local time, 29 Mar 00. Arizona does not observe daylight
savings time. Direct any questions or concerns to TSgt Ken Miller at
(623) 856-7179 X 255. All proposals must be faxed to (623) 856-3438 or
e-mail: ken.miller@luke.af.mil. ATTACHMENT 1 Veeder-Root Company
Guardian AST Monitoring System Product Description The Guardian AST
Monitoring System, Form NO 848590-110 is designed for compliance and
inventory control aboveground storage tanks where in-tank leak
detection is not required. The system is capable of monitoring one or
two tanks. FEATURES: The guardian has the following features: A
two-line 24-character-per-line display A cursor keypad and a keypad for
stepping through menu-driven programming and operation functions A red
warning indicator on the front panel to alert you of leaks and other
warning and alarm conditions An internal audible warning and alarm
indicator to alert you of leaks and other warning and alarm conditions.
The following probe and sensor is compatible with the Guardian AST
Monitoring System: 794390-YXX, High/Low Level Sensor. High/Low Level
Sensors indicate delivery and overfill conditions. Will fax picture
upon request! ATTACHMENT 2 Emergency Eyewash Unit Product Description
Deluxe Full Body/Eye Wash Emergency Station: Eyewash station has two
gentle spray outlet heads with a yellow ABS plastic bowl. Drench Shower
features stay open ball valve with pull rod and a yellow ABS plastic
shower head. Furnished with galvanized intermediate pipe and fittings
with 9_ floor flange. 1-1/4_ inlet and outlet Posted 03/17/00
(D-SN435581). (0077) Loren Data Corp. http://www.ld.com (SYN# 0117 20000321\Z-0014.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|