COMMERCE BUSINESS DAILY ISSUE OF MARCH 23,2000 PSA#2563USAED, Sacramento, Corps of Engineers, Contracting Division, 1325 J
Street, Sacramento, CA 95814-2922 48 -- MANUFACTURE TURBINE BYPASS VALVE, PINE FLAT DAM, CALIFORNIA SOL
DACW05-00-B-0008 DUE 051600 POC Beverly Hatfield, 916-557-5232 PLEASE
BE SURE TO PROVIDE A VALID E-MAIL ADDRESS WHEN FILLING OUT ORDERING
INFO ON OUR WEBSITE FOR ADDING YOUR NAME TO THE PLAN HOLDERS LIST. NOTE
THAT FAILURE TO FILL IN A VALID E-MAIL ADDRESS COULD RESULT IN YOU NOT
OBTAINING AMENDMENTS PUT OUT AGAINST THE SOLICITATION YOU ARE
ORDERING, AS WE ARE ONLY SENDING OUT AMENDMENTS TO SOLICITATIONS VIA
ELECTRONIC MAIL NOW. PROJECT TITLE: (Please note: This solicitation was
previously advertised as an RFP under the Solicitation number
DACW05-00-R-0016) Turbine Bypass Valve. This proposed contract is
UNRESTRICTED. JOB DESCRIPTION: Requirement is described as follows:
Manufacturer shall provide two energy dissipating, free discharge,
regulating valves, or either the sleeve or plate type multijet design.
Each valve shall be delivered to Pine Flat Dam (located approx. 30
miles east of Fresno, California). The manufacturer shall be
responsible for design, fabrication, shop testing, transportation, and
performance testing. One valve will be connected to a 66-inch pipe
flange and the other to a 48-inch pipe flange. The valves shall be
capable of producing a combined flow of at least 750-CFS of water
(temperature range of 32 to 80 deg F) when subjected to a static head
of 128.55 feet for the 48-inch valve and 118.25 feet for the 66-inch
valve. Each valve shall also be capable of producing a minimum flow
50-CFS or less at these head conditions. Finally, the valves shall be
capable of producing a combined flow of at least 900-CFS when subjected
to a static head of 365.05 feet for the 48-inch valve and 354.75 feet
for the 66-inch valve. The upstream static heads do not include head
losses in the upstream system. The net head on the valves should be
computed as the static head minus the upstream head losses. The
upstream head losses can be computed as k multiplied times the pipe
velocity head. For the 48 inch pipe, k=0.26 and the corresponding
velocity head is the velocity head in the 48 inch pipe. For the 66 inch
pipe, k=1.55 and the corresponding velocity head is the velocity head
in the 66 inch pipe. Both pipelines will have a minimum of 5 diameters
of straight piping immediately upstream of the valves. Valves shall be
capable of throttling all flows satisfactorily without cavitation at
the design pressure, shall be rated for a static pressure of 175 psi,
shall be equipped with ANSI flanges or with retaining flanges and
flange seals if the valves are wafer type, and shall include electric
(460/230 volt, 3 phase power) or hydraulic operators and all
appurtenances required for local push button operation. The operators
shall be sized for a minimum of 1.5 times the maximum force required to
actuate the valves. The manufacturer shall provide a five (5) year
guarantee that the valves will perform satisfactorily under actual
operating conditions. The manufacturer shall have a minimum of ten (10)
years' experience in the design and construction of similar valves,
which can be demonstrated to have operated successfully. SIC CODE: This
procurement will be conducted under SIC CODE 3491. The size standard
for this SIC Code is: 500 Employees. The acqusition method is
Invitation For Bid (IFB). For more information of the solicitation
please contact the Contract Specialist, Beverly Hatfield, at
916-557-5232. ORDERING PLANS AND SPECIFICATIONS: (AVAILABLE ON PAPER
COPY; FREE OF CHARGE) Plans and specifications for this project must be
ordered by the CUT OFF DATE of 04/10/2000 to ensure receipt of bid
sets. Plans and specifications can only be ordered electronically by
accessing internet address http://ebs.spk.usace.army.mil/ Please
complete the requested information to avoid a delay in your order.
Orders received beyond the CUT OFF DATE of 04/10/2000 will not be
honored. Plans and specifications will be mailed out on or about
04/14/2000. Because a limited number of sets will be reproduced, copies
are limited to one set per firm. All responsible sources may submit a
bid or proposal which will be considered by the agency. See Note 26
(See Commerce Business Daily, Monday edition). For a listing of all
Sacramento District projects, see Contracting Division's Internet Home
Page at http://ebs.spk.usace.army.mil/ which is updated daily. Please
note that all contractors and potential contractors must be registered
with the Central Contractor Registration (CCR) database effective May
31, 1998. For instruction on registration with the CCR please see our
webpage. Posted 03/21/00 (W-SN436787). (0081) Loren Data Corp. http://www.ld.com (SYN# 0206 20000323\48-0004.SOL)
48 - Valves Index Page
|
|