COMMERCE BUSINESS DAILY ISSUE OF APRIL 5,2000 PSA#2572USDA-Forest Service, Monongahela National Forest, 200 Sycamore Street,
Elkins, West Virginia 26241-3962 Y -- SADDLE LAKE DAM REHABILITATION SOL R9-21-00-13 DUE 053000 POC
Mary E. Saint Louis, Contracting Officer; 304/636-1800, ext. 265 The
Hoosier National Forest anticipates contracting for the Saddle Lake Dam
Rehabilitation on the Tell City Ranger District, Perry County, Indiana.
The work consists of construction of an auxillary spillway in Saddle
Lake Dam using Roller Compacted Concrete (RCC). The spillway is
approximately 8 feet deep and 200 feet wide located in the center of
the dam. The project will require an on-site concrete batch plant. The
contract time is 270 calendar days from the Notice to Proceed. The
project is estimated between $1,000,000.00 and $5,000,000.00. Drawings
and specifications will be available April 24, 2000 for a
non-refundable cost of $75.00. Checks or money orders should be made
out to the USDA, Forest Service and sent to the issuing activity along
with a mailing address and phone number. All responsible sources may
submit a bid for consideration. Posted 04/03/00 (W-SN440520). (0094) Loren Data Corp. http://www.ld.com (SYN# 0101 20000405\Y-0004.SOL)
Y - Construction of Structures and Facilities Index Page
|
|