COMMERCE BUSINESS DAILY ISSUE OF APRIL 11,2000 PSA#2576General Services Administration, Public Buildings Service (PBS),
Project Services (10PCPB), 400 15th Street, S.W., Auburn, WA
98001-6599 Z -- SOURCES SOUGHT -- CONSTRUCTION MANAGER AS CONSTRUCTOR, PROSPECTUS
ALTERATION FOR FEDERAL BUILDING AND US COURTHOUSE, ANCHORAGE, AK SOL
Reference-Number-AK0031AA DUE 042700 POC Jacquelyn Owens, Contract
Specialist, Phone 253-931-7675, Fax 253-931-7395, Email
Jacquelyn.Owens@gsa.gov WEB: SOURCES SOUGHT -- CONSTRUCTION MANAGER AS
CONSTRUCTOR,,
http://www.eps.gov/cgi-bin/WebObjects/EPS?ACode=P&ProjID=Reference-Number-AK0031AA&LocID=129. The General Services Administration
(GSA) is seeking potential sources of Construction Manager as
Constructor (CMc) services. CMc is defined as a firm engaged under
direct contract to a building owner, in this case the General Services
Administration (GSA), to provide design review, cost estimating,
scheduling and general construction services. The CMc shall be a member
of the project development team during the planning, design and
construction phases, along with GSA, and GSA's selected A-E firm.
PROJECT SUMMARY: Building Description: The project will occur in an
existing building of approximately 600,000 gsf, housing 1500 staff. The
building houses three Courtrooms serving 5 Judges, supported by the
U.S. Marshall's Service with detention facilities. The building is the
site of major offices for the U.S. Attorneys, (include list major
occupant agencies). The building systems are arranged in six unified
but vertically distinct modules varying in height from two to five
stories, plus a basement garage and roof top mechanical spaces. Office
space was arranged originally as a continuous open area on each story,
extending horizontally through several modules. Office space is now
extensively subdivided with walls and modular furniture. Building will
remain occupied during the project. Building occupants must remain
fully operational, but may be relocated. Synopsis of Work. Replace
existing HVAC digital controls with new digital controls, in two
increments: first, to take charge of existing HVAC systems, and
subsequently to be cut-over to control step by step the new HVAC
systems. Replace major portions of the existing HVAC systems, including
local air supply and re-heat systems, and perimeter heating systems
throughout the building, including all occupied office areas. Provide
additional new central fans and selectively modify other central
equipment. Replace the Fire Alarm system. Provide new toilet rooms in
selected locations. Replace existing roof with new EPDM IRMA system.
Replace major skylight with new monitor unit. Organization of Work.
Construction project is comprised of three sequential groups of work,
in the following order and captioned as follows. 1) PP/A1 -Replace HVAC
Controls. 2) PP/C1-B2 -- Replace Roofs -- Provide New Roof-top Fans. 3)
PPB1-A2 -Replace HVAC Systems -- Integrate Controls -- Add Restrooms.
Interested firms are invited to respond to this announcement by
providing the following information: company literature indicating
services provided, business size, geographical location(s) and/or
regional coverage of facilities. No solicitation exists at this time.
This request is intended only to identify sources of services. the
Government does not intend to award a contract on the basis of this
sources sought announcement or to otherwise pay for the information
requested. Posted 04/07/00 (A-SN442802). (0098) Loren Data Corp. http://www.ld.com (SYN# 0177 20000411\Z-0039.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|