ITEM DESCRIPTION FOR AC RESISTIVE LOAD BANK The General Services
Administration has authorized the use of this Commercial Item
Description. 1. SCOPE. This Commercial Item Description (CID) describes
an AC Resistive Load Bank. This is an AC (alternating current),
portable, console type load bank (electrical test set) used to test the
E-3, EC-18B, E-4, E-8 generators. 2. CLASSIFICATION. Equipment covered
by this CID shall be commercially available equipment and may be
modified to the extent necessary to meet the following characteristics.
3. SALIENT CHARACTERISTICS. 3.1 Safety and Environmental. The load bank
shall meet all safety and environmental requirements as specified in
MIL-PRF-28800 for the classification as stated herein. 3.2 Electrical
Power Sources. The load bank shall be self-contained and require no
power source to operate. All operating power for internal circuits and
instruments of the load bank shall be derived from the output power
supplied by the unit being tested. 3.3 Operating Temperature. The load
bank shall meet its performance and accuracy requirements in an
operating environment of 00C to +500C. 3.4 Non-operating Temperature.
The load bank shall meet its performance and accuracy requirements
after being in a nonoperating environment (Storage Temperature) of 100C
to +600C. 3.5 Mean Time Between Failures (MTBF). The load bank Mean
Time Between Failures (MTBF) shall be 2,000 hours. The lower test MTBF
shall be 2,000 hours and the upper test MTBF shall be 4,000 hours. 3.6
Calibration and Maintenance Adjustments. The design of the system shall
provide for readily accessible calibration adjustments and maintenance
adjustments. The calibration adjustments shall be provided by variable
value components adjustable by the use of simple means. The calibration
by substitution of selected components or parts is unacceptable unless
specifically approved. The calibration interval shall be a period of
one year or greater based on an operating time of 2,000 hours. 4.
PERFORMANCE CHARACTERISTICS. 4.1 Resistive Load Testing. The load bank
shall be capable of resistive load testing an AC ground generator set
rated at 120 Volts, 208 Volts 3 phase, and frequency of 400 Hz. The
minimum power requirement is 250 kW. 4.2 Metering. The load bank
control panel shall be equipped with panel meters for monitoring
voltage, frequency and current of the load bus. Meter accuracy shall be
3% full scale. 4.3 Connections for External Meters. The
load bank control panel shall have two connection points (banana jacks)
for external meters (digital multimeters). The connection points shall
be in parallel with existing load bank meters. 4.4 Phase Selector
Switch. The load bank shall have a selector switch on the control panel
for measuring the parameters of each phase of power (A, B, C). 4.5
Phase Rotation Indicator. The load bank shall have a phase rotation
indicator provided on the control panel. 4.6 E-F Circuit Indicator. The
load bank shall have an indicator light providedon the control panel to
indicate when the E-F circuit is complete. 4.7 AC Receptacles. The load
bank shall come equipped with four MS90362 AC receptacles (male
connectors) which are capable of connecting to four generator cables
(female connectors). 4.7.1 The electrical neutral of the load bank
shall be connected to the chassis ground of the E-F circuit (the return
side of the 28 VDC line of the E-F circuit). This is to prevent a
floating ground for certain generators. 4.8 Load Steps. The load steps
shall consist of 20, 40, 60, 80 and 100 percent; although a load bank
with a smaller load step resolution would be acceptable. The tolerance
of each load step shall be no more than 5%. 4.9 Shock Load
Capability. The load bank shall have a master load switch for shock
loading. 4.10 Resistor Elements. Resistor load elements shall be
adequately protected with, as a minimum, main line fusing of the load
bus. 4.11 Air Flow Failure. The load bank shall have protection
circuitry in case of fan failure oroverheating. 4.12 Transportability.
4.12 .1 The load bank shall be transportable, provided with wheels no
less than 8 inches in diameter. 4.12.2 It shall be constructed to have
the capability of being transported with a forklift. 4.12.3 The load
bank shall be constructed to withstand the bounces, vibrations, and
other conditions incident to transportation and operation. 4.13
Warranty. The load bank shall have, as a minimum, a 1-year standard
manufacturer s warranty. 5 QUALITY ASSURANCE PROVISIONS. 5.1 Product
Conformance. The products provided shall meet the salient
characteristics of this CID, conform to the producer s own drawings,
specifications, standards, and quality assurance practices, and is the
same product offered for sale in the commercial market. The government
reserves the right to require proof of such conformance. 5.2
Responsibility of Inspection. Unless otherwise specified in the
contract or purchase order, the contractor is responsible for the
performance of all inspection, examination, and test requirements
specified herein. Except as otherwise specified in the contract or
purchase order, the contractor may use his own facilities or any other
facilities suitable for the inspection requirements specified herein,
unless disapproved by the government. The government reserves the
right to set forth in this description where such inspections,
examinations and tests are deemed necessary to assure supplies and
services conform to prescribed requirements. 5.3 Examination. Each load
bank shall be visually examined to determine conformance with all
requirements of this description. 5.4 Operational Test. Each load bank
shall be operated, after complete assembly and prior to shipment, to
ensure all moving parts are functioning according to the manufacturer
s requirements. 6. PACKAGING. Preservation, Packaging, Labeling, and
Marking shall be as specified in the contract or order. 7. NOTES.
MIL-PRF-28800 Test Equipment for use with Electrical and Electronic
Equipment, General Specification for Unless otherwise indicated, copies
of federal and military specifications, standards and handbooks are
available from the standardization document order desk, 700 Robins Ave.
Bldg. No. 4, Section D, Philadelphia, PA. 19111-5094. Ph.
(215)697-2179. Other phone extensions at above No.: 0158, 0159, 0162,
and 2667. The following product(s) are known to have previously met the
requirements of this CID and need not resubmit bid samples or
certification. All other manufacturers must meet the requirements of
this CD and submit to bid testing and certification as required.
Manufacturer Cage P/N NSN Avtron 01014 K696D24864 6150-01-390-3241YA
The following manufacturers have products, which are potentially
acceptable; however, they must meet the requirements of this CID and
submit to bid sample testing and certification. Manufacturer Cage P/N
NSN Simplex 78308 Dynamite 300 Custodians: Preparing Activity: Air
Force-99 Air Force-82 Reviewer Project 6625- Posted 04/10/00
(D-SN443006). (0101) Loren Data Corp. http://www.ld.com (SYN# 0373 20000412\61-0005.SOL)
61 - Electric Wire and Power and Distribution Equipment Index Page
|
|