COMMERCE BUSINESS DAILY ISSUE OF APRIL 28,2000 PSA#2589USPFO for Alabama, P.O. Box 3715, Montgomery, AL 36109-0715 Y -- REPLACE BASE ENGINEER MAINTENANCE COMPLEX, BIRMINGHAM IAP (ANG),
BIRMINGHAM, AL SOL DAHA01-00-B-0001 DUE 071000 POC SSG Willie Sikes,
Contract Specialist, 334-271-7333 This project consists of the
construction of the Base Engineer Maintenance (BEM) Complex. This
facility has a total authorized square footage of 20,300 SF. The BEM
Complex consists of offices, shops and storage to support Base
Facilities Maintenance, the Civil Engineer Squadron, Prime BEEF
Training, and the Disaster Preparedness Section. The complex is a
single story structure. The overall building space allocation separates
the Storage drive-thru facility from the Administrative/Shop functions
on the site. Standing seam pitched roofs, red brick veneer, and
architectural detailing compliance are required. The interior finishes
selected have commercial grade closed loop carpet, painted gypsum
board/metal stud walls and suspended acoustical ceilings for the
offices and classroom. Bathroom floors & walls to have ceramic tile
finish. Ceilings to be moisture resistant gypsum board. The "utility"
functions such as the Storage Building & Shop areas have durable
CMU walls (sealed & painted), sealed concrete floors and painted
exposed structure. The structural system designed utilizes common
materials and exceeds the minimum code requiring wind loading
resistance. Spread concrete footings and grade beams support load
bearing reinforced CMU walls. Light gauge steel trusses form the sloped
roof structure with a metal deck and standing seam roof assembly.
Reinforced concrete slabs on grade form the floor system. All
structural components are non-combustible. Electrical power for the
buildings will be obtained from the existing underground power system.
Energy efficient lighting is in accordance with ANG Design Policy and
will be centrally managed. Integration into the DDC management system
is included. Area lighting for the parking lot (195 parking spaces)
and work areas surrounding the building are accomplished through the
uses of building mounted and pole mounted fixtures. Telephone and fiber
optic cables are included to the building through the existing
underground duct bank system. A fire detection system will be installed
with all equipment necessary for connection to the existing base-wide
fire detection system. Estimated cost of construction is between
$1,000,000.00 and $5,000,000.00. A non-refundable charge, unknown at
this time, will be required for each set of plans and specifications.
Bid documents will be available from the USPFO for Alabama, ATTN:
AL-US-P, P O Box 3715, Montgomery, AL 36109-0715. Plans and specs will
be made available for reviewing at the F W Dodge Plans Room,
Birmingham, AL and the office of the Base Civil Engineer, Birmingham
IAP (ANG), Birmingham, AL. This project is 100% unrestricted. IFB
Number DAHA01 00 B 0001 will be issued with an anticipated issue date
of June 1, 2000, and a bid opening on or about July 10, 2000. Posted
04/26/00 (W-SN448958). (0117) Loren Data Corp. http://www.ld.com (SYN# 0104 20000428\Y-0007.SOL)