|
COMMERCE BUSINESS DAILY ISSUE OF MAY 4,2000 PSA#2593Naval Surface Warfare Center, Code 1163, 300 Highway 361, Crane, IN
47522-5001 59 -- RADIO FREQUENCY CABLE SOL N00164-00-Q-0202 DUE 051200 POC Ms.
Diane Pearson, Code 1163W7, telephone 812-854-5201, FAX 812-854-3805;
Ms. Luann Shelton, Contracting Officer WEB: click here to download copy
of RFQ modifcation, http://www.crane.navy.mil/supply/announce.htm.
E-MAIL: click here to contact via e-mail, pearson_d@crane.navy.mil.
This combined synopsis/solicitation is modified to incorporate updated
attached drawings. This modification incorporates the following FAR
Clause: FIRST ARTICLE APPROVAL-GOVERNMENT TESTING (SEP 1989) (FAR
52.209-4) (a) The Contractor shall deliver 1 unit(s) of Lot/Item 0001
& 0005 within 21 calendar days from the date of this contract to
the Government at Naval Surface Warfare Center, 300 Highway 361, Crane,
IN 47522 for first article tests. The shipping documentation shall
contain this contract number and the Lot/Item identification. The
characteristics that the first article must meet and the testing
requirements are specified elsewhere in this contract. (b) Within 14
calendar days after the Government receives the first article, the
Contracting Officer shall notify the Contractor, in writing, of the
conditional approval, approval, or disapproval of the first article.
The notice of conditional approval or approval shall not relieve the
Contractor from complying with all requirements of the specifications
and all other terms and conditions of this contract. A notice of
conditional approval shall state any further action required of the
Contractor. A notice of disapproval shall cite reasons for the
disapproval. (c) If the first article is disapproved, the Contractor,
upon Government request, shall submit an additional first article for
testing. After each request, the Contractor shall make any necessary
changes, modifications, or repairs to the first article or select
another first article for testing. All costs related to these tests are
to be borne by the Contractor, including any and all costs for
additional tests following a disapproval. The Contractor shall furnish
any additional first article to the Government under the terms and
conditions and within the time specified by the Government. The
Government shall act on this first article within the time limit
specified in paragraph (b) of this clause. The Government reserves the
right to require an equitable adjustment of the contract price for any
extension of the delivery schedule or for any additional costs to the
Government related to these tests. (d) If the Contractor fails to
deliver any first article on time, or the Contracting Officer
disapproves any first article, the Contractor shall be deemed to have
failed to make delivery within the meaning of the Default clause of
this contract. (e) Unless otherwise provided in the contract, the
Contractor-(1) May deliver the approved first article as a part of the
contract quantity, provided it meets all contract requirements for
acceptance and was not consumed or destroyed in testing; and (2) Shall
remove and dispose of any first article from the Government test
facility at the Contractor's expense. (f) If the Government does not
act within the time specified in paragraph (b) or (c) of this clause,
the Contracting Officer shall, upon timely written request from the
Contractor, equitably adjust under the Changes clause of this contract
the delivery or performance dates and/or the contract price, and any
other contractual term affected by the delay. (g) The Contractor is
responsible for providing operating and maintenance instructions, spare
parts support, and repair of the first article during any first article
test. (h) Before first article approval, the acquisition of materials
or components for, or the commencement of production of, the balance of
the contract quantity is at the sole risk of the Contractor. Before
first article approval, the costs thereof shall not be allocable to
this contract for (1) progress payments, or (2) termination settlements
if the contract is terminated for the convenience of the Government.
(i) The Government may waive the requirement for first article approval
test where supplies identical or similar to those called for in the
schedule have been previously furnished by the Offeror/Contractor and
have been accepted by the Government. 1st article testing will consist
of nondestructive testing. Testing will be performed in actual
conditions. The delivery schedule is as follows: 1st article units are
due 3 weeks ARO; the Government requires a maximum of 2 weeks to
perform 1st article testing; final units are due 4 weeks after
successful completion of 1st article testing. Posted 05/02/00
(W-SN450425). (0123) Loren Data Corp. http://www.ld.com (SYN# 0229 20000504\59-0006.SOL)
59 - Electrical and Electronic Equipment Components Index Page
|
|