Loren Data Corp.

'

 
 

COMMERCE BUSINESS DAILY ISSUE OF MAY 4,2000 PSA#2593

Naval Surface Warfare Center, Code 1163, 300 Highway 361, Crane, IN 47522-5001

59 -- RADIO FREQUENCY CABLE SOL N00164-00-Q-0202 DUE 051200 POC Ms. Diane Pearson, Code 1163W7, telephone 812-854-5201, FAX 812-854-3805; Ms. Luann Shelton, Contracting Officer WEB: click here to download copy of RFQ modifcation, http://www.crane.navy.mil/supply/announce.htm. E-MAIL: click here to contact via e-mail, pearson_d@crane.navy.mil. This combined synopsis/solicitation is modified to incorporate updated attached drawings. This modification incorporates the following FAR Clause: FIRST ARTICLE APPROVAL-GOVERNMENT TESTING (SEP 1989) (FAR 52.209-4) (a) The Contractor shall deliver 1 unit(s) of Lot/Item 0001 & 0005 within 21 calendar days from the date of this contract to the Government at Naval Surface Warfare Center, 300 Highway 361, Crane, IN 47522 for first article tests. The shipping documentation shall contain this contract number and the Lot/Item identification. The characteristics that the first article must meet and the testing requirements are specified elsewhere in this contract. (b) Within 14 calendar days after the Government receives the first article, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval. (c) If the first article is disapproved, the Contractor, upon Government request, shall submit an additional first article for testing. After each request, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall furnish any additional first article to the Government under the terms and conditions and within the time specified by the Government. The Government shall act on this first article within the time limit specified in paragraph (b) of this clause. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule or for any additional costs to the Government related to these tests. (d) If the Contractor fails to deliver any first article on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract. (e) Unless otherwise provided in the contract, the Contractor-(1) May deliver the approved first article as a part of the contract quantity, provided it meets all contract requirements for acceptance and was not consumed or destroyed in testing; and (2) Shall remove and dispose of any first article from the Government test facility at the Contractor's expense. (f) If the Government does not act within the time specified in paragraph (b) or (c) of this clause, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay. (g) The Contractor is responsible for providing operating and maintenance instructions, spare parts support, and repair of the first article during any first article test. (h) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government. (i) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the Offeror/Contractor and have been accepted by the Government. 1st article testing will consist of nondestructive testing. Testing will be performed in actual conditions. The delivery schedule is as follows: 1st article units are due 3 weeks ARO; the Government requires a maximum of 2 weeks to perform 1st article testing; final units are due 4 weeks after successful completion of 1st article testing. Posted 05/02/00 (W-SN450425). (0123)

Loren Data Corp. http://www.ld.com (SYN# 0229 20000504\59-0006.SOL)


59 - Electrical and Electronic Equipment Components Index Page