COMMERCE BUSINESS DAILY ISSUE OF MAY 26,2000 PSA#2609193rd Special Operations Wing (PAANG) LS/LGC, 79 Mustang Alley,
Harrisburg International Airport, Middletown, PA 17057-5079 Y -- ATC TRAINING FACILITY SOL DAHA36-00-R-0008 POC Contracting
Officer MSgt Charles R. Bishop (717) 948-2360 E-MAIL: ERROR --,
charles.bishop@paharr.ang.af.mil. This project is for the construction
of new facilities for the Pennsylvania Air National Guard at
Johnstown-Cambria County Airport, Johnstown, PA. The scope of the work
includes full responsibility for complete construction services to
include any subcontracts and construction quality control. The
Government inspector's function is to ensure compliance with the
specifications and to verify the required level of construction quality
is achieved in the finished product. The scope generally includes a
primary facility, and site improvements on two tactical training sites.
The primary facility is a 20,350 square foot Composite Support Facility
including administrative areas, electronics maintenance shops,
generator maintenance shops, and warehouse storage space. The
construction is generally concrete foundations, masonry cavity walls,
concrete floor slabs, steel supporting structures, roofed partly with
single ply EPDM and partly with standing seam metal roof. Site
improvements generally include clearing, grading, utility work, and
concrete and asphalt paving. The tactical training sites are a Mobile
Radar Site and Mobile Tower Site. These site improvements generally
consist of paved access roads, large concrete equipment pads, site
utilities, and a 675 square foot building for utility terminations,
latrine facilities, and a break room area. Work on the tactical
training areas is inside the airport air operations area and site
access and work schedules will be coordinated with the Airport
Authority and Air Traffic Control Tower. Compliance with Federal
Aviation Administration guidelines to properly mark equipment in this
area is required. The project generally includes construction of
utilities between the sites to provide electrical, communications,
water and force main sanitary sewer. The utility construction includes
boring under a state highway and several runways and taxiways in
addition to a several thousand feet of open trenching. The Pennsylvania
Air National Guard has no existing utilities on these sites and it will
be the Contractor's responsibility to make all arrangements for
utilities to be used during the construction with the utility provider.
Estimated project range is between $1,000,000 and $5,000,000.
Solicitations will be available o/a 19 June 2000. This acquisition is
issued persuant to the "Business Opportunity Development Reform Act of
1988" and subsequant award will be considered UNRESRICTED therefore
all responsible concerns may request this solicitation and submit a
bid. To be awarded this contract the concern must be registered on the
Central Contract Register. No telephone requests, only written
requests for this solicitation package received within 10 days of the
date of the solicitaion will be accepted. A pre-proposal conference
will be held in the conference room of the Johnstown-Cambria County
Airport, Johnstown, PA at 9:00 AM on 6 July 2000. Posted 05/24/00
(W-SN458399). (0145) Loren Data Corp. http://www.ld.com (SYN# 0172 20000526\Y-0008.SOL)
Y - Construction of Structures and Facilities Index Page
|
|