COMMERCE BUSINESS DAILY ISSUE OF JUNE 2,2000 PSA#2613USDA Forest Service, Ochoco National Forest, PO Box 490, Prineville, OR
97754 Y -- RECONSTRUCT ROCK CREEK TRAIL SOL 7-2000-R15 DUE 071800 POC
Cecilia Rogers, Procurement Technician, 541/416-6534 or fax
541/416-6661 This project consists of reconstructing Rock Creek Trail,
11.19 Kilometers. Included in the project are 16 sections of relocated
trail, totaling 1.26 kilometers and 1.26 kilometers of trail
obliteration for the abandoned existing trail. Work consists of
clearing and grubbing, excavation, trail restoration, logging out,
construction of water bars, drain dips, and rock fords. Also, amoring,
underdrains and a log stringer foot bridge. Power tools can be used
for construction. This project is located on the Paulina Ranger
District in Crook County, Oregon. This project is approximately 130
kilometers east of Prineville, Oregon. Estimated start work date is
August 7, 2000 and completion date is September 15, 2000. Price Range
is $25,000-$100,000. Bonding is required. Posted 05/31/00 (W-SN460275).
(0152) Loren Data Corp. http://www.ld.com (SYN# 0108 20000602\Y-0003.SOL)
Y - Construction of Structures and Facilities Index Page
|
|