COMMERCE BUSINESS DAILY ISSUE OF JUNE 5,2000 PSA#2614C -- SOLE SOURCE PROCUREMENT NOTIFICATION -- A-E SERVICES FOR
GEOTECHNICAL REVIEW OF PLANS AND SPECIFICATIONS AND FOUNDATION DESIGN
REPORT FOR THE PORTUGUES ARCH DAM NEAR PONCE, PUERTO RICO C -- Under
the authority of FAR 6.302-1, the US Army Corps of Engineers intends to
negotiate on a sole source basis to Don Banks, Ph.D. Work shall consist
of, but not be limited to, bidibility and constructibility review on
advance sets of plans and specifications to include drilling and
grouting; independent technical review on an advance copy of a
foundation design report; evaluating and verifying the accuracy of
design assumptions; providing a written report and identifying areas of
potential high claim exposure; participating in a review conference;
identifying specific areas where assumptions or misunderstandings may
cause increased costs for the Contractor and/or the Government;
furnishing comprehensive report of major potential problems identified
during review of plans and specifications and design documents; and
recommending and/or assembling other data that may be required.
Jacksonville District requires technical advice, in a timely manner, as
the effectiveness of the grouting is evaluated and decisions on what
future remedial actions may be needed. It would be very costly to the
Government, both financially and technically and would seriously affect
the overall schedule, to develop a new consultant's knowledge base of
the Portugu s Dam site. Interested concerns shall submit documentation
demonstrating the following qualifications by 19 June 2000: (1) firm
shall clearly demonstrate specialized experience in the design and
construction of large civil works construction, especially concrete
dams. The firm shall have broad geotechnical experience and background,
with a strong knowledge of rock mechanics, rock bolting, blasting,
tunnel stabilization, drilling and grouting techniques, and engineering
geology. The firm shall be capable of providing court testimony, if
required, and shall be competent in oral and written communications,
with the ability to develop and render recommendations in a timely
manner. In addition, the firm shall be familiar with the way the U.S.
Army Corps of Engineers conducts its construction business with
standard construction contracts and the contract administrative
procedures which support the construction claims and appeals
procedures; (2) firm shall have a professional staff consisting of, but
not limited to, geotechnical engineers, engineering geologists, and/or
all necessary supervisory and administrative personnel required to
review and analyze plans and specifications. All professional staff who
work on this contract shall be registered engineers or registered
geologists; (3) firm shall have extensive experience analyzing the
complex, highly fractured, metasediment foundations such as that found
at the Portugu s Dam Site; (4) firm shall have a strong knowledge of
construction bidding procedures. Questions concerning this procurement
may be addressed to Kathie Duke at 904-232-3713. WEB: Click here to
view further information, http://www.saj.usace.usace.army.mil. E-MAIL:
Click here to contact the Contract Specialist,
Kathleen.B.Duke@usace.army.mil. Posted 06/01/00 (W-SN460529). Loren Data Corp. http://www.ld.com (SYN# 0378 20000605\SP-0018.MSC)