COMMERCE BUSINESS DAILY ISSUE OF JUNE 6,2000 PSA#2615Department of the Air Force, Air Education and Training Command, Little
Rock AFB, Contracting Squadron, 642 Thomas Avenue, Bldg 642, Little
Rock AFB, AR, 72099 99 -- REPLACE ARNOLD DRIVE LANDSCAPE SOL F03602-00-T0227 DUE 061200
POC Todd Davis, Contracting Specialist, Phone 501-987-3855, Fax
501-987-8119, Email todd.davis@littlerock.af.mil -- Ken Spohn,
Contracting Specialist, Phone 501-987-6470, Fax 501-987-6624, Email
WEB: Visit this URL for the latest information about this,
http://www.eps.gov/cgi-bin/WebObjects/EPS?ACode=P&ProjID=F03602-00-T02
27&LocID=583. E-MAIL: Todd Davis, todd.davis@littlerock.af.mil. This is
a combined synopsis/solicitation for commercial item prepared in
accordance with the format in FAR Subpart 12.6 as supplement with
additional infromation included in this notice. This constiutes the
only solicitation; quotes are being requested and written solicitation
will not be issued. This solicitation is being issued as a Request For
Quotation number F03602-00-T0227. The Solicitation document and
incorporated provisions and clauses are those in effect through Federal
Acquisition Cirular 97-17. This is a 100% set aside for small business
concerns. The SIC code for this solicitation is 0782. The small
business size standard is $5.0 million dollars. The contractor shall
provide all material, supervision, equipment and supplies to remove
approximately 230 shrubs and plant approximately 175 shrubs along
Arnold Drive, Little Rock AFB, AR, and other work as indicated in the
following statement of work. Item 1: Shrub, Silverberry (5gal)
Estimated 130 EA. Item 2: Shrub, Cherry Laurel (5gal) Estimated 25 EA.
Item 3: Shrub, Leyland Cypress (5gal) Estimated 20 EA. Item 4: Sodding
Estimated 8400 SF. Item 5: Planting, Heavy Soil (5gal) Estimated 175
EA. Item 6: Remove Existing Red Tip Shrubs Estimated 230 EA. Item 7:
One Year Maintenance of New Shrubs 1 LS. Performance period for Items
1-6 is 21 calendar days. Period of performance for 1 year maintenance
is 365 calendar days after acceptance of Items 1-6. The purpose of
existing shrubs is to provide a natural screen wall between Base
Housing and Arnold Drive. Some shrubs have been infected and or killed
by the spotted leaf fungus, thus making density of plants inadequate
in some areas. The attached drawings indicate approximately where
shrubs are to be removed and planted (see attached drawings). The
contractor shall provide a sketch or drawing indicating the proposed
layout of new shrubs, to include quantity and type of shrubbery used.
The layout should utilize all three varieties to the extent possible to
provide an attractive view-scape along Arnold Drive. The shrubs shall
be planted at spacing appropriate to each variety so that at maturity
the screen wall has a uniform density and provides maximum privacy in
housing areas. In areas where shrubs will be planted under power lines,
the variety of shrubs, when fully mature, will not extend within 8 feet
of the power lines (without requiring pruning). Debris shall be removed
from the base promptly, and as feasible, all equipment and materials
shall be removed or secured at the end of each day. The Contractor is
responsible for the daily cleanup of all work areas and debris that has
escaped from the construction site. Removal of debris and other
material shall be handled, transported, stored, and disposed of by the
Contractor and his Subcontractors in accordance with all applicable
federal, state or local laws, ordinances, regulations, court orders or
other types of rules or rulings having the effect of laws. These
restrictions shall apply both on and off base. Contractor shall submit
for approval the name and location of the proposed landfill site and
types of material for which the site is certified. Contractor shall
also submit with the regular progress reports, tickets showing yardage,
tonnage dumped, and estimates by yds or lbs of each type of material
dumped. The new shrubs shall be maintained by the contractor for one
year to ensure the shrubs live. Within the 1 year maintenace period, if
any of the new shrubs die or become diseased, the contractor will be
responsible for the replacement of the dead or diseased shrubs. The
contractor, as part of the required maintenance, will be responsible
for any watering in excess of rainfall. The government will not water
the new shrubs during the one-year maintenance period. A source of
water will be available on base for the contractor's use during
planting operations and the maintenance period. Little Rock Air Force
Base duty hours are 7:30 a.m. to 4:30 p.m. all days of the week except
Saturday, Sunday and Federal Holidays. No work will be performed at
any time other than normal work week without obtaining written approval
of the Contracting Officer. (If weekend or evening work is required due
to utility outages or other requirements, such work shall be with prior
approval of the Contracting Officer, and accomplished at no additional
cost to the Government.) The Contractor is responsible to visit the
project site prior to, and during, the course of construction to verify
existing conditions, actual sizes, and other requirements outlined in
this statement of work. As work nears completion, the Base Civil
Engineering Construction Inspector (CI), as the Contracting Officer's
designated representative, and the Contractor's quality control
representative or his superintendent will thoroughly inspect the work
and generate a deficiency (punch) list. When this list has been
cleared, the CI will schedule a preliminary inspection for the CE
Construction Manager (CE/CM) to participate, using organization and
government specialists of the systems installed under the contract.
When alldeficiencies are corrected, the Contractor shall request a
final inspection. The final inspection will be conducted by the CE/CM,
and attended by the Contractor and the Contracting Officer
representative. For phased work, this process may be repeated for each
phase. Workers shall not enter the occupied portion of the building to
use restrooms, telephones, or other facilities. Smoking is prohibited
in all government facilities under this contract. The Contractor is
responsible to obtain all necessary security passes for his personnel
and vehicles. Contractor_s superintendent shall be equipped with a
cellular telephone and be reachable by telephone at any time during the
normal workday. The cellular phone number shall be a local call from
Little Rock AFB. Contractor_s superintendent shall be reachable, by
telephone or pager, 24 hours a day, seven days a week for the duration
of the project. Payment for shrubs and planting will be made at the
contract unit price per each and shall be full compensation for
preparation of bed, setting shrubs, fertilizer, and etc. complete in
place. Sodding in place will be measured by square foot as measured
along slope distances of areas disturbed during landscaping activities.
Payment will be made at the unit price bid per square foot for
_sodding_ which price will be full compensation for the preparation of
sub-grade, sod, lime fertilizer, and water including labor, tools,
equipment, and incidentals necessary to complete the work. Removal of
existing shrubs will be measured per each shrub actually removed.
Payment for shrub removal will be made at the contract unit price each
and shall be full compensation for removal, hauling, and disposal. One
year maintenance of shrubs will be paid at the contract lump sum price
and shall be full compensation for providing all labor required for
watering/maintaining shrubs and all labor and materials required for
replacing any shrub that becomes diseased or dies during the
maintenance period. Payment will be made after the performance period
for Item 7. Acceptance time will be 10 days from bid opening date. The
following provisions apply to this solicitation: 52.212-1 Instructions
to Offerors-Commercial Items(Mar 00), 52.212-3 Offeror Representations
and Certifications-Commercial Items(FEB 00), 252.225-7000 Buy American
Act-Balance of Payments Program Certificate(SEP 99); and the following
clauses 52.223-5 Pollution Prevention and Right-to-Know
Information(APR 98), 252.204-7004 Required Central Contractor
Registration(MAR 00), 252.212-7001 Contract Terms and Conditions
Required to Implement Statutes or Executive Orders Applicable to
Defense Acquistion of Commercial Items(MAR 00) including clause
incorporated by reference under section (a) 252.225-7001 Buy American
Act and Balance of Payments Program(MAR 00), 52.212-4 Contract Terms
and Conditions-Commercial Items(MAY 99), 52.212-5 Contract Terms and
Conditions Required to Implement Statutes or Executive
Orders-Commercial Items(FEB 00) including clauses incorporated by
reference under section(b) 52.222-21 Prohibition of Segregated
Facilities(FEB 99), 52.222-26 Equal Opportunity(FEB 99), 52.222-35
Affirmative Action for Disabled Veterans and Veterans of the Vietnam
Era, 52.222-36 Affirmative Action for Workers with Disabilities(JUN
98), 52.232-33 Payment by Electronic Funds Transfer-Central Contractor
Registration(MAY 99), also clauses included by reference under
section(c), 52.222-41 Service Contract Act of 1965 as Amended(MAY 89),
52.222-42 Statement of Equivalent Rates for Federal Hires(MAY 89),
Department of Labor Wage Determination No.:94-2033-Revision No.: 14,
Rev: 8-16-99, applies. A written notice of award or acceptance of
offer, mailed or otherwise furnished to the successful bidder within
the time specified in the offer shall result in a binding contract
without further actions by either party. Bidders responding to this
announcement shall submit a price for this project along with the
information required in 52.212-1 and completed copy of provision
52.212-3 to 314 CONS/LGCA1, 642 Thomas Avenue, Little Rock AFB, AR
72099, by 10 Jun 00, at 4:30PM Local Time. Faxed bids will be accepted
at 501-987-8119. Site visits can be arranged by calling SSgt. Todd
Davis at 501-987-3855. All responsible sources will be considered.
Posted 06/02/00 (D-SN461070). (0154) Loren Data Corp. http://www.ld.com (SYN# 0278 20000606\99-0003.SOL)