Loren Data Corp.

'

 
 

COMMERCE BUSINESS DAILY ISSUE OF JUNE 8,2000 PSA#2617

U.S. Property & Fiscal Office For Kansas, 2737 S Kansas Ave, Attn: Contracting, Topeka, KS 66611-1170

Y -- CONSTRUCT LIVE MUNITITONS RAMP, MCCONNELL AFB, KS SOL DAHA14 00 5300 POC Lt Tony Diaz, (785) 274-1218 Contract Administrator or Mr. Tom Coleman (785) 274-1211, Contracting Officer E-MAIL: Click here to contact the contracting officer via, tom.coleman@ks.ngb.army.mil. Construct B1B Live Munitions Ramp for the Kansas Air National Guard at McConnell AFB, Wichita, Kansas. Project constructs approximately 79,425 SY B-1B aircraft-parking apron (18-in. thick concrete, 4-in. cement treated drainage layer, and 8-in. lime treated subgrade (LTS)) adjacent to existing taxiway. Project constructs 50-ft wide, primarily asphalt over LTS, shoulders adjacent to new concrete parking apron. Project grading requires large amounts of earthwork (cut/fill). Project constructs reinforced concrete box (RCB) culvert to extend existing storm drainage pipes under new concrete apron. Project constructs concrete drainage flume, five new storm inlets, and 10,000-gal spill capacity oil/water separator. Project constructs 8-in. fire protection main with fire hydrants and semi-flush taxiway lights at perimeter of apron with two lighted taxiway signs. Project provides ramp area lighting. Project provides five 7-ft W x 21-ft H x 76-ft L metal barricades with compacted granular fill with individual lighting and communications support. Airfield obstruction lighting to be mounted on top of new area lighting and barricades. Project provides miscellaneous other pavements including 12-in. concrete road and 5/7-in. asphalt pavements on LTS. Apron and support pavements will be stripped. Project demolishes existing asphalt pavement, and existing security fence and communications cable to be demolished and replaced. Project relocates pad-mounted transformer. Project caps and replaces two monitoring wells. Project dismantles and relocates 2,700 SF metal building to new site with pavement and electrical support. Project demolishes existing overhead electrical power system to include poles length of ramp and constructs new 12470-volt underground primary service. Two primary pad switches will be required to feed pad-mounted transformers. Project provides remote camera, site surveillance capability. Project constructs new 1,300 SF metal building. New facility is climate controlled with telephone/LAN service (copper andfiber), CCTV, and P.A. system. Project installs domestic water service, two-1,500 gal concrete wastewater holding tanks, and required electrical support for new facility. Bidders must submit with their bid data verifying accessibility to operational, heavy-duty, fully energized, self propelled paver-finisher designed specifically for placing, consolidating, and finishing high quality pavement within guidelines of project specifications. Pre-approval of machine is required prior to award. Bidders shall submit with their bid data verifying minimum 10 years work experience with major concrete paving operations using paver-finisher machine. Pre-approval of work experience is required prior to award. This project has not received final design approval. It is anticipated that the solicitation will be issued on or about 11 July 2000. Estimated cost of this project is between $5 and $10 million. All responsible bidders may obtain a bid set by submitting a cashier's check or money order payable to the U.S. Treasury in the amount of $258.00. This fee is non-refundable. Plans and specifications will be sent to you automatically upon there release and approval. SIC Code: 1771 Request for bid sets should be mailed to USPFO/KS, ATTN: Contracting Officer, 2737 S. Kansas Ave., Topeka, KS 66611-1170. All responsible sources may submit a bid which will be considered. Posted 06/06/00 (W-SN461800). (0158)

Loren Data Corp. http://www.ld.com (SYN# 0118 20000608\Y-0019.SOL)


Y - Construction of Structures and Facilities Index Page