COMMERCE BUSINESS DAILY ISSUE OF JUNE 9,2000 PSA#2618Commander, Southern Division, Naval Facilities Engineering Command,
2155 Eagle Drive, P. O. Box 190010, North Charleston, SC 29419-9010 Z -- REPLACE UNDERGROUND CABLE IN OFFICER'S HOUSING AT NAVAL WEAPONS
STATION, GOOSE CREEK, SC SOL N62467-00-B-8277 DUE 062600 POC POC: Lori
Chestnut, Contract Administrator 843-764-4112 ext. 3046 WEB:
www.esol.navfac.navy.mil, www.esol.navfac.navy.mil. E-MAIL:
lloydca@efdsouth.navfac.navy.mil, chestnutlh@efdsouth.navfac.navy.mil.
Replace underground electrical cable in officer's housing located at
the Naval Weapons Station, Goose Creek, SC. SIC# 1623. Estimated
between $100,000 and $200,000. IT IS MANDATORY TO SCHEDULE A SITE VISIT
AND CONTRACTOR MUST BE IN THE CENTRAL CONTRACTOR REGISTERATION PRIOR TO
SUBMITTING A BID. (SEE WWW.CCR2000.COM) CONTRACTOR'S NOT REGISTERED IN
CCR WILL NOT BE CONSIDERED. TO SCHEDULE A SITE VISIT POC: NIKKI BUTLER
843-764-4112 EXT. 3052 OR CALL BEEPER# 888-528-9243. THE WORK INCLUDES
FURNISHING ALL LABOR, MATERIAL, EQUIPMENT AND SUPERVISION FOR 1)
Replacement of existing 15 KV primary distribution system components
including cables, raceways, and single phase pad mounted transformers.
2) Work shall be completed within 240 calendar days. This includes 15
calendar days to allow for mailing of contract award and
submission/approval of required bonds. 3) Liquated damages shal be the
sum of $200.00 for each calendar day of delay. 4) The basis of bid
shall be lump sum for the entire work, complete. 5) Prepare a
computerized critical path method (CPM) schedule that includes proposed
engineering, procurement, construction and testing activities. The CPM
schedule shall cover the time from contract award/notice to proceed to
the contract completion date. The CPM schedule shall incorporate labe,
equipment and quantity resource data as well as cost information. The
principles and definitions of the terms used herein shall be set forth
in AGCA CPS and Contract Clause "FAR 52.236-13, Schedules for
Construction Contracts". 6) Contractor shall use the current version of
the Sure Trak Software by Primavera Systems, Inc. which shall be
capable of operating in a Windows environment. If the contractor
chooses to use an equally capable program, the Contractor shall convert
all data into Primavera Machine Readable Format (Lotus, D-Base, Excel,
etc.) prior to submission of all schedule inputs, including but not
limited to the initial schedule, monthly updates, and changes to the
schedule. All required network analysis submissions and updates shall
be submitted on 3-1/2 inch double sided, high density disks. The disks
submittal requirement shall be in addition to any hard copy submittal
required. SITE VISITS ARE MANDATORY AND REQUEST OF SOLICITATION
PACKAGES MUST BE REQUESTED IN A TIMELY MANNER PRIOR TO THE CLOSING
DATE. SOLICITATION PACKAGES ONLY AVAILABLE ELECTRONICALLY. (GO TO
WWW.ESOL.NAVFAC.NAVY.MIL) If further information is contact Lori
Chestnut 843-764-4112 ext. 3046.***** Posted 06/07/00 (W-SN462296).