|
COMMERCE BUSINESS DAILY ISSUE OF JUNE 14,2000 PSA#2621Naval Research Laboratory, Attn: Code 3230, 4555 Overlook Avenue, SW,
Washington, DC 20375-5326 58 -- ACOUSTIC PROJECTION SYSTEM FOR ACTIVE MEASUREMENTS SOL
N00173-00-R-CB02 POC Contact, Contract Specialist, Cheri R. Burkhardt,
Code 3230.CB (202) 767-6542, Contracting Officer, Carol A. Parnell,
Code 3230, (202) 767-6542 WEB:
http://heron.nrl.navy.mil/contracts/rfplist.htm,
http://heron.nrl.navy.mil/contracts/rfplist.htm. This notification is
in response to questions that came about from the previous synopsis,
which appeared in the May 11, 2000 edition of the Commerce Business
Daily. The following are the stated questions with the answer to each
question: Question 1: The specification requires conductor pairs for
each element in the array. Would an alternative scheme such as a shared
common conductor that reduces the size and cost of the
electromechanical cable be considered acceptable if it does not lead to
unacceptable array performance? Answer to Question 1: No. We would not
favor the proposed alternative scheme. The government wants to be able
to control the beam, and so the amplitude and phase of each array
element individually. Furthermore, if the common conductor breaks, the
array is out of operation: whereas, if one of the conductor pairs
breaks, the array is still operable (though at reduced source level).
Question 2: Is a slip-ring assembly for each cable conductor required
for the winch? Answer to Question 2:No. A slip-ring assembly is not
required. Question 3: Is a level-wind mechanism required for the winch?
Answer to Question 3: No. A level-wind mechanism is not required.
Question 4: Paragraph 8.3 is titled "Winch and Handling System". The
winch requirement is defined but is there a requirement for a Handling
System such as an A-frame? Answer to Question 4: No. There is not a
requirement for a handling system. Paragraph 8.3 of the specification
should be titled "Winch". Question 5: What primary power will be
available to power the Power System of Paragraph 3.3 and Winch 8.3?
Answer to Question 5: The projection system will be used on
research-grade vessels which generally have a full range of power
systems. It can be assumed that 220/440 VAC 3-phase @ 50 amps
available. Question 6: In para. 3.1.b -- Towability -- "towable in a
stable vertical configuration ". Define parameters for vertical
stability and vertical positioning of the tow body (projector source).
Do you have requirements for roll, pitch and yaw? Is there any
tolerance for movement of the tow body (projector source)? Is the towed
body (projector source) allowed to rotate? Answer to Question 6: The
projector system will be used to make a variety of scientific
measurements included among them is the measurement of bottom
backscatter as a function of angle. For the measurements to be of
value, the projector beam pattern must be known, and it must remain
reasonably stable throughout the measurement period. The government,
therefore, has a "stable vertical configuration" requirement. The
projector beam pattern has a vertical axis and is azimuthally
omnidirectional therefore not necessary to describe in terms of roll,
pitch, and yaw. The government will specify in terms of (a) a maximum
deviation of the beam pattern from vertical and (b) the maximum rate at
which the deviation may vary. The projection unit, accordingly, should
remain vertical to within 4 degrees to a nominal tolerance of 1 degree
when towed at speeds of up to 4 knots in the absence of currents. As to
movement of the tow body, the government has no strong tolerances on
its vertical excursions -- 1 to 2% of the water depth is a typical
tolerance. The projector beam pattern is to be omnidirectional
azimuthally, therefore there is no acoustic reason to constrain the tow
body from rotating to some degree. Rotational forces must not be such
that the mechanical integrity of the system is jeopardized; the tow
body may not be permitted to rotate to the point of damaging the tow
cable or the electrical or mechanical connections. Question 7: What is
the current profile in the area where acoustic measurements will be
taken: In other words, what is the maximum current that the towed body
(projector source) will see? Answer to Question 7: The majority of our
measurements will be in water currents where it would range from 0 to
1 knots. Question 8: What is the configuration of the anchor? Is it
hydrodynamically shaped? Answer to Question 8: No particular anchor in
mind. The government so determine,in the technical specifications,
that some amount of tensioning weight will be required to achieve and
maintain vertical stability of the sonar projection unit, when towed at
speeds up to 4 knots. The size, weight, and shape of any anchor
required to achieve this stability will be influenced by the design of
the projection system itself. The offeror must provide guidance on
what sort of anchor is required to meet the specification and state any
requirement in the Deployment and Recovery Plan. It must be consistent
with the specification Sonar Projector construction 3.2.e.4 and Tow
Cable Strength 3.4.a. Question 9: What type(s) of vessels will be
towing the projector source? Answer to Question 9: The ships will
primarily be oceanographic research vessels and be 100 to 300 feet in
length, typically. Ship will be outfitted to deploy and recover
oceanographic equipment of this size and larger and have ample deck
space to work and accommodate any winch and handling system this
projection system requires. Laboratory space to house shipboard
computers, amplifiers, etc. and similarly there is provision for
powering scientific equipment. The precise characteristics vary from
platform to platform. Question 10: In para. 3.2.b -- Source Level -- Is
the 210 dB re uPa at 1 m a "band level" for 70% of 1.5 -- 5 kHz ( and
200 dB for 85% of the same range)? Answer to Question 10: The source
level figures are source spectrum levels. The source level of the
projection unit must be at least 210 decibels re 1 micropascal @ 1
meter as measured in a 1-Hz band over at least 70% of the interval from
1.5 to 5 kHz, and at least 200 decibels re 1 micropascal @ 1 meter as
measured in a 1-Hz band over at least 85% of the interval from 1.5 to
5 kHz. Question 11: At what Sea State will the towed body be operating
in? Answer to Question 11: The government plans to deploy and recover
the projection system in sea states between 0 and 3. Question 12:
Section 3.2. Is there any tolerance on verticality of the projectors
while under tow? Answer to Question 12: The projection unit should
remain vertical to within 4 degrees to a nominal tolerance of 1 degree
when towed at speeds of up to 4 knots in the absence of currents.
Question 13: Section 3.2 (c) Part 3. Please confirm there is no side
lobe level specification for the array when steered through plus minus
30 degrees. Answer to Question 13: The only side-lobe level
specification is for horizontal steering. It is desirable, although, to
maintain side-lobe control over as a broad a range of frequencies and
steering angles as possible. Question 14: Section 8.6. Confirm that
optional calibration at USN Seneca Lake is for the single elements only
and not for the acoustic projector array, in the case where an array of
elements is offered. Answer to Question 14: Optional in-water
calibration is for single elements only, the case where an array of
elements is offered. Question 15: Indicate whether a single (RS-232
type) digitized signal carried on a single conductor pair from the ESM
is an acceptablealternate. Answer to Question 15: A single digital
signal for each engineering sensor carried on a single conductor pair
from the ESM is an acceptable alternative. The digital signals must be
isolated to prevent coupling into the analog source signals. Question
16: The CBD posting indicates that the government reserves the right
to exercise options 3 through 6 up to a quantity of eight times. (a)
For Option 3 ESM, does this imply pricing is required for a quantity of
1 through 8 ESM, or a quantity of 2 through 16 (i.e. the technical
specification speaks to "pairs" of ESMs). (b) For Option 3 ESM, confirm
the additional quantities are for spares and do not require signal
conductors in the tow cable and deck cable, (c) Option 4 -- Projection
elements does this imply bidder must provide pricing for 9 baseline
system variants (i.e. baseline, baseline plus 1 additional element,
baseline plus 2 additional elements . . .) and /or some of the up to
quantity 8 of this option for spares purposes and not installed inthe
base line system, (d) Option 5 -- Power amplifier, same question as (c)
above. Answer to Question 16: (a) Pricing is required for a pair of
ESMs. The government has the option to purchase up to 8 pairs. (b) The
tow cable and deck cable have to include all the wiring for power and
signal for a pair of ESMs as described in Option 3 (0006). The
additional ESMs would be spares. (c) Option 4 (CLIN 0007), if
exercised, will be only one time. Offerors may provide pricing for as
many potential baseline configurations as they wish. (d) The government
may exercise Option 5 (CLIN 0008) up to 8 times for individual
amplifiers. Question 17: The CBD refers to inspection and acceptance 30
days after completion of training. As this solicitation only comprises
a portion of a full towable system, confirm that inspection and
acceptance does not include at sea performance testing. Answer to
Question 17: Inspection and acceptance does not include at-sea
performance testing. Question 18: In Section 3.1 paragraph 3.
Operational depth, there is reference to meeting the depth
specification without cavitation or compensation. Would you define
compensation? Is this a reference to motion/heave compensation? Answer
to Question 18: Compensation refers to maintaining a constant
output-level calibration during projection unit motion, including heave
and tidal effects. The government prefers not having to use active
depth compensation, such as a SCUBA bottle. Question 19: In Section 3.4
regarding the Electromechanical Tow Cable, it indicates that the cable
must be double armored. One option to consider is a Kevlar armor
package and use two layers of served Kevlar strands the same way that
steel armor would be applied. Is double Kevlar armor acceptable or do
you require steel armor? Answer to Question 19: The government requires
steel armor. Question 20: Section 8.3 (Option) there is no mention of
a slip-ring associated with the winch. Assume option exercised, the
government will want a slip-ring assembly and want the offeror to
install and terminate the tow cable on the winch. Is this correct?
Answer to Question 20: A slip-ring is not required. If the option were
exercised, the government would want the successful offeror to install
and terminate the tow cable on the winch. URL
http://heron.nrl.navy.mil/contracts/rfplist.htm Posted 06/12/00
(W-SN463823). (0164) Loren Data Corp. http://www.ld.com (SYN# 0193 20000614\58-0004.SOL)
58 - Communication, Detection and Coherent Radiation Equipment Index Page
|
|