COMMERCE BUSINESS DAILY ISSUE OF JUNE 22,2000 PSA#2627193rd Special Operations Wing (PAANG) LS/LGC, 79 Mustang Alley,
Harrisburg International Airport, Middletown, PA 17057-5079 Y -- ATC TRAINING FACILITY SOL DAHA36-00-R-0008 POC Contracting
Officer MSgt Charles R. Bishop (717) 948-2360 E-MAIL: click here to
contact the contracting officer via, charles.bishop@paharr.ang.af.mil.
This project is for the construction of new facilities for the
Pennsylvania Air National Guard at Johnstown-Cambria County Airport,
Johnstown, Pa. The scope of the work includes full responsibility for
complete construction services to include any subcontracts and
construction quality control. The Government inspector's function is to
ensure compliance with the specifications and to verify the required
level of construction quality is achieved in the finished product. The
scope generally includes a primary facility, and site improvements on
two tactical training sites. The primary facility is a 20,350 square
foot Composite Support Facility including administrative areas,
electronics maintenance shops, generator maintenance shops, and
warehouse storage space. The construction is generally concrete
foundations, masonry cavity walls, concrete floor slabs, steel
supporting structures, roofed partly with single ply EPDM and partly
with standing seam metal roof. Site improvements generally include
clearing,grading, utility work, and concrete and asphalt paving. The
tactical training sites are a Mobile Radar Site and Mobil Tower Site.
These site improvements generally consist of paved access roads, large
concrete equipment pads, site utilities, and a 675 square foot
building for utility terminations, latrine facilities, and a break room
area. Authority and Air Traffic Control Tower. Compliance with Federal
Aviation Administration guidelines to properly mark equipment in this
area is required. The product generally includes construction of
utilities between the sites to provide electrical, communications,
water and force main sanitary sewer. The Pennsylvania Air National
Guard has no existing utilities on these sites and it will be the
Contractor's responsibility to make all arrangements for utilities to
be used during the construction with the utility provider. Estimated
project range is between $1,000,000 and $5,000,000. Solicitations will
be available o/a 27 June 2000. A pre-bid conference will be held in
theconference room of the Johnstown-Cambria County Airport, at 9:00 AM
on 6 July 2000. This acquisition is issued pursuant to the "Business
Opportunity Development Reform Act of 1988" and subsequent award will
be considered UNRESRICTED therefore all responsible concerns may
request this solicitation and submit a bid. To be awarded this contract
the concern must be registered on the Central Contract Register. No
telephone requests, only written requests by General Contractors for
this solicitation package received within 10 days of the date of the
solicitation will be accepted. Posted 06/20/00 (W-SN466703). (0172) Loren Data Corp. http://www.ld.com (SYN# 0106 20000622\Y-0027.SOL)
Y - Construction of Structures and Facilities Index Page
|
|