Y -- FUEL SYSTEMS MAINTENANCE DOCK, ELMENDORF AFB, ALASKA

Notice Date
December 28, 2001
Contracting Office
US Army Corp of Engineers -- Alaska -- Military Works, P. O. Box 898, Anchorage, AK 99506-0898
ZIP Code
99506-0898
Solicitation Number
DACA85-02-R-0009
Response Due
April 5, 2002
Point of Contact
Pacita Cayas, 907/753-2553, FAX 907/753-2544
E-Mail Address
US Army Corp of Engineers -- Alaska -- Military Works (pacita.f.cayas@usace.army.mil)
Description
Design, permitting, site preparation and construction of an Aircraft Fuel Systems Maintenance Hangar. Demolition of the existing Fuel Systems Maintenance Hangar including ACM Disposal and Elimination of Interior Columns in hangar space will be included as a Priced Options. The project will construct approximately a 4,000 SM Fuel Systems Maintenance Hangar to replace the Fuel Systems Maintenance functions of the existing Hanger 10. Award of this project will be based on the best value approach considering technical evaluation factors and price. An adjectival method of evaluation will be used to evaluate the technical evaluation factors. The technical evaluation factors include Qualification: Experience, Past Performance, and Organization in descending o rder of importance; Technical Approach: Technical Solution, Betterments and Innovation, Schedule, and Commissioning with Technical Solution, Betterments and Innovation, of equal weight and more important than Schedule which is more important than Commissi oning; and Product Information: Product information will be evaluated as equal in importance to Technical Solution, Betterments and Innovation. Technical Solution will be more important than Qualifications. Price will be subjectively evaluated conside ring Best Value and Realism. Contractor's Quality control will be a requirement for this contract. Large Business concerns submitting proposals shall comply with the Federal Acquisition Regulation 52.219-9 regarding the requirement for a subcontracting p lan. Contractors shall be required to commence work within 10 days after Notice to Proceed and complete work 1,066 calendar days after receipt of Notice to Proceed. Provisions will be included for liquidated damages in case of failure to complete the wor k in the time allowed. Performance and Payment bonds are required. The estimated design and construction cost for this project is between $10,000,000 and $15,000,000. THIS SOLICITATION WILL BE ISSUED USING ELECTRONIC BID SETS (EBS) AND PROVIDED ON COMPA CT DISKS-READ ONLY (CD-ROM) AT NO CHARGE. http://ebs.poa.usace.army.mil NAICS code is: 233310 (formerly SIC code 1541). Open to Large and Small Businesses.
Web Link
Army Single Face to Industry (http://acquisition.army.mil)
Record
Loren Data Corp. 20020101/YSOL001.HTM (D-362 SN516150)

Y - Construction of Structures and Facilities Index  |  Issue Index |
Created on December 28, 2001 by Loren Data Corp. -- info@ld.com