SOURCES SOUGHT

Z -- FTW363 Family Housing Replacement Construction

Notice Date
1/22/2010
 
Notice Type
Sources Sought
 
NAICS
236118 — Residential Remodelers
 
Contracting Office
Department of the Army, U.S. Army Corps of Engineers, USACE District, Alaska, ATTN: CEPOA-CT, P. O. Box 6898, Elmendorf AFB, Alaska, 99506-6898, United States
 
ZIP Code
99506-6898
 
Solicitation Number
W911KB-10-S-FTW363
 
Archive Date
3/9/2010
 
Point of Contact
Kevin Maloy, Phone: 907-753-5594
 
E-Mail Address
kevin.j.maloy@usace.army.mil
(kevin.j.maloy@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Description
This is a Sources Sought Announcement. This is NOT a request for Proposal and does not obligate the Government to any contract award. The purpose of this announcement is a MARKET SURVEY to determine the interest and capability of Small Business, HUBZone, 8(a), or Service Disabled Veteran Owned Business contractors for the following proposed Design-Build project: Complete and perform corrective work to primary facility housing units and supporting facilities site work for 110 single Family housing units constructed as part of the combined FY04 Family housing project Taku Gardens Fort Wainwright, Alaska. Requirements for primary facilities include: flushing, disinfection and other commissioning steps for activation of the water, sewer, heating and ventilation systems; replacement of all batteries in battery operated equipment; replacement of hot water heating system circulating pumps; repair or replacement of damaged floor and wall finishes: and other minor work that is necessary to make the units operational after remaining idle since 2007. Requirements for supporting facilities include: site survey; site grading to the original design; roadways; curbs; sidewalks; driveways; patios; fencing; stoops; entries; paths; skating rink, drainage structures; grass; trees; shrubs; site furnishings, signage, pedestrian bridges, playgrounds, mailboxes, warming huts, benches, and waste receptacles; utilities work to include testing, flushing, disinfection and commissioning of the water distribution system; inspection and commissioning of the piping and pumping components of the sanitary sewer system; commissioning of the hot water district heating system including cleaning, testing, operational verification, and renewal of the water/glycol fluid, and any required corrective work; completion of the two site mechanical service buildings including water and sewer service connections, ventilation systems, controls, piping configuration, testing, commissioning, and repairs as required; completion and adjustments to the site electrical distribution system including commissioning, testing, completion of electrical pole guying, replacing water-damaged transformers, repairs to corroding ground connections, and adjustment of components to proper elevations to match with final site grading; installation of the site exterior lighting system in coordination with buried utilities; reconstruction, completion, and commissioning of the site telecommunications systems in coordination with the site grading plan and other buried utilities. Complete start up requirements of primary facility and construction of supporting infrastructure for 110 single Family housing units. Contract duration is 450 days and estimated cost range is between $10,000,000 and $25,000,000. NAICS is 236118. Size limitation is $33.5M. All interested Small Business, HUBZone, 8(a), or Service Disabled Veteran Owned Business contractors should notify this office in writing by mail or email on or before 22 February 2010, 12:00 pm, Alaska Time. Responses should include: (1) Identification and verification that the company is certified by the Small Business Administration as a HUBZone or 8(a) contractor or self-certified as a Service Disabled Veteran Owned Business, as applicable; (2) The level (dollar amount) of performance and payment bonding capacity that the company could attain for the proposed project; (3) Past Experience - Provide descriptions of projects substantially complete or completed within the last five years which are similar to this project in size, scope, and dollar value. With each project experience provided, include the date when the project was completed or will be complete, location of the project, contract amount and size of the project, the portion and percentage of work that was self performed, whether the project was design/build or not, and a description of how the experience relates to the proposed project; (4) A statement of which portion of the work that will be self-performed and how it will be accomplished; and (5) A statement of experience with design and construction in sub-arctic climates. Send responses to the U.S. Army Corps of Engineers, Alaska District, P.O. Box 6898, ATTN: CEPOA-CT-M (Kevin Maloy), Elmendorf AFB, Alaska 99506-0898 or email to kevin.j.maloy@usace.army.mil. This is NOT a request for proposal and does not constitute any commitment by the Government. Responses to this sources sought notice will be used by the Government to make appropriate acquisition decisions. All interested sources must respond to future solicitation announcements separately from responses to this market survey.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA85/W911KB-10-S-FTW363/listing.html)
 
Place of Performance
Address: Taku Gardens, Ft. Wainwright, Alaska, 99703, United States
Zip Code: 99703
 
Record
SN02047394-W 20100124/100122235042-4ce307eb31a542394962f6b9eb67cdaa (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.