COMMERCE BUSINESS DAILY ISSUE OF MAY 19,1998 PSA#2098General Services Administration, Public Buildings Service, P. O. Box
25546, Denver, CO 80225-0546 Z -- REPLACE CHILLERS, PIERRE, SOUTH DAKOTA SOL GS-08P-98-JCC-0032 DUE
070898 POC Barbara A. Barbour 303-236-1770 x283 SIC Code 1711. Project
Location: FB/PO/CTHS, 225 S. Pierre St, Pierre, SD. Performance
Period: 190 calendar days. Estimated price range: $1,000,000 --
$5,000,000. Presolicitation Notice to be issued o/a 5/15/98. IFB to be
issued o/a 6/08/98. BOD o/a 7/08/98. Scheduled site visit anticipated
for 6/17/98. Contractor shall provide all management, superintendence,
labor, materials, equipment, parts, machinery, etc. to perform the
following work: Base Bid Provide selective abatement of asbestos
insulation on HVAC piping. Replace the two centrifugal chillers and
required accessories with new high-efficiency chillers. Replace
associated cooling towers and condenser water chemical treatment
system. Provide new condenser and chilled water pumps, selective
demolition and installation of electrical motor control equipment to
support HVAC mechanical work, new mechanical room ventilation system,
test and balance of chilled and condenser water systems and air handler
chilled water coils. Perform commissioning (i.e. functional performance
testing) of chilled and condenser water systems. Repair and refurbish
roll filters in air handling units, AHU-1,2,3,4,5,6 and pre-heat coil
intake roll filter located in the rooftop penthouse. Repair and
refurbish the existing pneumatic control systems throughout the
building. A new air compressor and filter/dryer assembly shall be sized
for current load and installed. Existing pneumatic tubing shall be
cleaned ("bubbled") to remove contaminants. All pneumatic controllers
in mechanical rooms shall be replaced. Replace existing chilled water
system compression tank located in the 4th fl. Mechanical room. Replace
motor starters on AHU-1,2,3,4,5,6, and 8 in mechanical rooms. Option
Bid Remove existing pneumatic building control system and install a new
building energy management and control system (EMCS). (Do not
repair/refurbish existing pneumatic system.) Upgrade the existing
(Andover System) remote master control terminal at GSA Office, Federal
Building, Aberdeen, SD to interface with the existing building control
system at that site plus the new EMCS at the Pierre, SD FB/PO/CT.
Provide automatic control valve operators to room sensors. Work
includes selective demolition of piping, valves, and fittings and
selective demolition of asbestos pipe insulation, new control valves
and pipe fittings, new room sensor control via EMCS of the terminal
fin-tube heating units, and re- commissioning of fin-tube heating
control systems. This procurement is made pursuant to the Small
Business Competitiveness Demonstration Program; therefore, acquisition
is unrestricted. All responsible sources will be considered. All
request for plans/specifications or planholder list must be submitted
in writing to the GSA Business Service Center (8AB), P.O. Box 25006,
Denver, CO 80225-0006. In lieu of mailing request, FAX request to the
BSC at 303-236-7403. Phone requests will not be accepted. Planrooms,
exchanges, etc. are requested to note BSC address and/or FAX number in
publications. DO NOT MAIL OR PHONE REQUESTSTO THE ABOVE POC. (0134) Loren Data Corp. http://www.ld.com (SYN# 0137 19980519\Z-0020.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|