COMMERCE BUSINESS DAILY ISSUE OF JUNE 16,2000 PSA#2623Department of the Air Force, Air Force Materiel Command, AAC -- Air
Armament Center, AAC/PK, 205 West D Avenue, Suite 433, Eglin AFB, FL,
32542-6864 Z -- CONSTRUCT STORAGE FACILITY, BUILDING 1343, EGLIN AFB, FL SOL
F08651-00-R0027 DUE 081500 POC Lillie Loggins, Contract Specialist,
Phone (850)882-5628 x 5271, Fax (850)882-9442, Email
loggins@eglin.af.mil -- Sheila Kingman, Contract Specialist, Phone
(850)882-5628 x 5274, Email kingman@eglin.af.mil WEB: Visit this URL
for the latest information about this,
http://www.eps.gov/cgi-bin/WebObjects/EPS?ACode=P&ProjID=F08651-00-R00
27&LocID=1182. E-MAIL: Lillie Loggins, loggins@eglin.af.mil. Eglin AFB
FL, has a requirement for the construction of an 80-foot by 30 foot,
pre-engineered, addition on one side of Hangar 1343, the work will be
performed atHangar 1343, Eglin AFB, Okaloosa County, Florida. "THIS IS
A TRADE OFF" (PERFORMANCE PRICE TRADE-OFF) ACQUISITION. Award will be
made based upon "Best Value" to the Government in accordance with FAR
15.3. The Government reserves the right to award a contract to other
than the lowest proposed price. This project includes furnishing all
plant; labor, equipment and materials to remove or alter construction
to an 80 foot by 30 foot pre-engineered, addition on one side of Hangar
343. This facility will be used as a storage facility for aircraft
cargo pallets, cargo straps and nets, pallet bags and other mobility
equipment. In general work consists of constructing an open area
facility with no interior walls, although chain link fences will divide
the space into three areas, each with its own overhead door for vehicle
access. The space will be heatedand ventilated, and will be protected
by a sprinkler system. Lighting and receptacles will be provided and
the space will be connected to the building fire alarm system. The lump
sum contract price shall include the cost of performing the work as
shown on the drawing and as specified hereafter. The estimated dollar
range is between $100,000.00 and $250,000.00. The bid acceptance period
is 120 days. All responsible sources may submit a proposal, which shall
be considered by the Agency. The above general description of work does
not in any way limit the responsibility of the contractor to perform
all work and furnish all plant, labor, equipment, and materials
complete in accordance with the plans and specifications. The Proposal
due date of 16 Aug 00 IS AN ESTIMATED DATE. All responsible sources
may submit a proposal, which shall be considered by the agency. No
response to this notice is necessary and no source list shall be
maintained. Paper copies of this solicitation will not be issued, but
the Request for Proposal (RFP) will be available on the Federal
Government's Electronic Posting system (www.eps.gov.). See Note 26
Posted 06/14/00 (D-SN464661). (0166) Loren Data Corp. http://www.ld.com (SYN# 0153 20000616\Z-0023.SOL)